Districts Impacted
Counties Impacted
Greene
Route Impacted
60
MM
ZZ
Work Type
Intersection Improvements
Planning Phase
Project Timeline
February 28, 2022
Public meeting
6-8 p.m. at the Republic Community Center
Community Rooms A and B, 711 E Miller Rd, Republic
6-8 p.m. at the Republic Community Center
Community Rooms A and B, 711 E Miller Rd, Republic
Summer 2024
Project B awarded to construction contractor
Fall 2024
Project B construction
Spring 2025
Project D awarded to construction contractor
Summer 2025
Project D construction
Winter 2025
Project B complete
Fall 2026
Project D complete
Projects A & C
Schedule to be determined upon approval of funding
Project Displays/Maps
- Fact Sheet
- Project Vicinity Map
- Projects A, B, C & D Alternative 1
- Projects A, B, C & D Alternative 2
- Projects A, B, C & D Alternative 3
- Location Study Report
- Traffic Study Report
- Railroad Closure Map
- Proposed Roundabout at Route MM and Farm Road 160
- Proposed Intersection at U.S. Route 60 and Farm Road 103
- Proposed Roundabout at Route M and Route ZZ
- Pathways of Progress: A Property Owners Guide on Land Acquisition for Transportation Improvements
Project highlights:
MoDOT is seeking public input on 4 (four) proposed Greene County Route MM/ZZ improvement projects that are being evaluated to reduce traffic delays and increase safety at various intersections in Republic.
Project A:
- Widening of Route MM to 5 lanes from Route 360/James River Freeway to Farm Road 160
- Intersection improvements
- Estimated Construction Cost: $18 million (currently unfunded)
-
City of Republic applying for RAISE Grant through OTO
Project B:
- Widening Route MM to 5 lanes between I-44 and north of Route 360/James River Freeway
- Estimated Construction Cost: $10.3 million
- City of Republic applying for RAISE Grant through OTO
- Cost share with the City of Republic
- Construction: 2024
Project C:
- Build new Route MM between Route 60 and Route ZZ (Wilson’s Creek Boulevard)/Route M (Republic Road)
- Build bridge over BNSF Railroad at Farm Road 103
- Possible roundabout on new Route MM at Route ZZ (Wilson’s Creek Boulevard)/Route M (Republic Road)
- Estimated Construction Cost: $29.4 million (currently unfunded)
Project D:
- Roundabout on Route MM (Brookline Avenue) at Farm Road 160
- Build bridge over BNSF Railroad south of Haile Street
- Build new Route MM between Farm Road 160 and Route 60
- Remove U.S. Route 60 intersection at Commercial Avenue/Farm Road 103
- Build intersection connecting new Route MM with Route 60 west of Route 60 intersection at Commercial Avenue/Farm Road 103
- Close BNSF Railroad crossings at Route 60 and Farm Road 170, Route MM and Farm Road 168, and East Haile Street/Orr Street in Brookline
- Pedestrian trail between Route MM (Brookline Avenue)/Farm Road 160 and Route 60
- Estimated Construction Cost: $33.8 million
- City of Republic applying for RAISE Grant through OTO
- Construction: 2025