Counties Impacted
Osage
Route Impacted
50
CC
Work Type
Intersection Improvements
Planning Phase

Traffic is congested on U.S. Route 50 at Route CC and Technology Drive, especially during work and school rush hours. The addition of signals and turn lanes will improve safety and traffic flow at these two intersections.

Project Milestones

Complete

The Missouri Department of Transportation and their consultants designed intersection improvements that include:

  • Adding signals at the intersection of U.S. Route 50 and Route CC.
  • Adding signals at the intersection of U.S. Route 50 and Technology Drive.
  • Pavement widening at both intersections for the addition of turn lanes.

The estimated cost for constructing these improvements as of May 30, 2023, is $2.1 million. This cost may change.

milestone_icon
Complete
Public Input
Comment period: June 15 - 30, 2023

Public Meeting

An open-house style public informational meeting was held Thursday, June 15, 4:30 to 6 p.m. at the Osage County Community Center in the Function Room. The Community Center is located at 1769 U.S. Route 50, Linn, MO. Attendees could come and go as they please at any time from 4:30 to 6 p.m., as there was no formal presentation. Members of the project team were on hand to answer questions and provide information. Exhibits showing the current planned work were available.

Attendees could leave comments with the project team, either verbally or written. Written comments were also accepted by mail, postmarked on or before June 30, to: 

Osage County U.S. Route 50/Route CC Intersection project, 1511 Missouri Boulevard, Jefferson City, MO 65102

Meeting materials

At the online public meeting links below are all exhibits that were displayed the in-person meeting. The open comment period closed June 30, 2023.

milestone_icon
Not Started
Contract Letting, Award & Notice to Proceed

The project is currently scheduled to go out for bids as part of MoDOT's May 2024 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their June 2024 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

At this time, construction is anticipated to begin in summer 2024 with completion late in 2024.

The roadway is expected to remain open during construction with single-lane closures during working hours.

milestone_icon

Q: Why is MoDOT changing these intersections?

A: Traffic is congested on U.S. Route 50 at Route CC and Technology Drive, especially during work and school rush hours. The addition of signals and turn lanes will improve safety and traffic flow at these two intersections.

 

Q: Will U.S. Route 50, Route CC or Technology Drive be closed during construction?

A: At this time, the roadway is expected to remain open, but motorists will encounter lane closures throughout the construction process.

 

Q: Who can I contact if I have further questions?

A: Questions about the project may be directed to MoDOT's Customer Service team at CDCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636). Please refer to the Osage County Intersection Improvement Project at U.S. Route 50 and Route CC in emails or by phone to ensure your questions are directed to the correct personnel.

 

Q: How can I stay updated on the project's progress?

A: Keep visiting this page, follow MoDOT's Central District on social media, sign up for email/text alerts at Modot.org, or use the form below to sign up for project-specific updates. 

Proposed Project Plans and Meeting Handout

Project Limits

View an aerial image of the plans showing the beginning and end limits of the project.

Design Plans

View details of the proposed plans for intersection improvements along U.S. Route 50 at the Route CC and Technology Drive intersections.

Meeting Handout

View the informational handout provided to attendees at the Public Information Open House held June 15, 2023, at the Osage County Community Center in Linn, MO.