Counties Impacted
Buchanan
Route Impacted
169
FF
Work Type
Intersection Improvements
In Progress

news Project Need and Purpose

The intersection of U.S. Route 169 and Buchanan County Route FF was identified for an intersection improvement project that will improve the turning radius for tractor-trailers. The project also will include resurfacing the intersection and extending a culvert near the intersection. 

Project Progress

Complete
Planning, Design & Right of Way Acquisition Phase

MoDOT's Planning and Design team is designing a project to resurface the intersection and allow more turning room for tractor trailers. MoDOT will contact property owners to obtain the right-of-way and easements required for this project.

milestone_icon
Complete
Public Meeting

A public open house meeting was held on Wednesday, January 22 at the Missouri Department of Transportation's Northwest District Office.

If you were unable to attend the open house, two other opportunities for public comment are available through Wednesday, February 5, 2025.

  1. Use the comment form below.
  2. Mail your comments to:             

               Buchanan Route FF Intersection Improvement Project 

               Missouri Department of Transportation

                3602 North Belt Highway

                St. Joseph, MO 64506

          All comments must be postmarked by Wednesday, February 5, 2024.

Map to District Office Conference Center

milestone_icon
Complete
Contract Letting, Award and Notice to Proceed

The contract for the intersection improvement project was part of the January 2026 letting for contractor bids. The contract was awarded by the Missouri Department of Transportation Commission at its February 2026 meeting to Leavenworth Excavating & Equipment Company, Inc. for $1,243,802.80.

milestone_icon
In Progress
Construction

The intersection improvement project is currently under construction, and is scheduled to be completed by August 2026.

milestone_icon

Frequently Asked Questions:

Q: Will the road be closed during construction?

A: During construction, U.S. 169, Route FF and 49th Street will be closed during a portion of the project.

Q: Will there be a planned detour for this project?

A: There is no signed detour planned for this project.

Q: Is right-of-way required for this project?

A: Yes, some right-of-way will be required for this project. MoDOT will work with property owners to determine the right-of-way and reach an agreement ahead of the project's construction.

Q: How can I stay updated on the project's progress?

A: Sign up for project-specific updates using the form below.

news Project News

  • Buchanan County Gene Field Road Bridge over I-29 now open

    06/27/2026

    ST. JOSEPH, Mo. – The Gene Field Road Bridge over Interstate 29 in St. Joseph is now open following a bridge replacement project. Clarkson Construction Company, working with the Missouri Department of Transportation, reopened the bridge to traffic...

  • Planned Roadwork for Northwest Missouri, June 29-July 5

    06/26/2026

    St. Joseph, Mo. – The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in the Northwest Missouri region for the week of June 29-July 5.

    MoDOT will limit road construction...

Webform
Have Project Questions or Feedback? Please use the form below to let us know.
*
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
Image
This image is a Google Maps screenshot of the intersection of U.S. Route 169 and Route FF in Buchanan County

Need More Information?

We're here to help! If you're looking for additional information, you can contact us at: 

  • nwcr@modot.mo.gov
  • 1-888-ASK-MODOT (275-6636) - reference Buchanan County U.S. Route 59 Intersection Improvement Project