Counties Impacted
Franklin
Jefferson
Route Impacted
47
WW
Hogan Road
Work Type
Guardrail Upgrades
Planning Phase

Project Summary

The Missouri Department of Transportation will upgrade aging guardrails to current standards in various locations  along Route 47 and Hogan Rd. in Franklin County and Route WW in Jefferson County. Specific areas for upgrades are:

  • Route 47 (Franklin County)  - Between Route 30 and Highway FF
  • Hogan Rd. (Franklin County)  - From the state maintenance line  to Viaduct St. 
  • Route WW (Jefferson County) - Between Route Y and Route H

The cost of the project is $541,000, and it is expected to be completed within 46 days of starting construction, pending weather conditions.

Project Milestones

Complete
Design Phase
March 2022
milestone_icon
Complete
Project Advertised
April 2022
milestone_icon
Complete
Contract Awarded
June 2022
milestone_icon
Complete
Construction Begins
July 2022
milestone_icon
Complete
Project Completed
Fall 2022
milestone_icon

IMPACT TO TRAFFIC

The project will have minimal impact to traffic.  There will be flaggers and signs directing motorists through work zones.  The below maps outline the areas to receive upgrades.

Who to Contact

Contact Photo
Stephen O'Connor Profile Picture
Stephen O'Connor, P.E.
Title
Area Engineer
Department
St. Louis District
Contact Info

Area Engineer, Franklin & Jefferson County Area 

(314) 453-5021

Stephen.OConnor@modot.mo.gov

Contact Photo
Photo of Christine Redhage
Christine Redhage
Title
Resident Engineer, Jefferson and Franklin Counties
Department
St. Louis District
Contact Info

Phone:  (314) 435-5018

Email:  Christine.Redhage@modot.mo.gov