Project Summary
The Missouri Department of Transportation will work on pavement resurfacing, pipe replacement, upgrade guardrail and replace signage from Route 30 to Pickles Ford Road, including a culvert replacement over Dry Branch Road and a culvert extension over Hoosier Creek.
Project Milestones
Not Started
Project Advertised
December 2025
Not Started
Project Letting Date
January 2026
Not Started
Project Award Date
February 2026
Not Started
Anticipated Notice to Proceed
March 2026
Frequently Asked Questions
What is the estimated cost of construction?
The estimated cost of construction is $3.05 million.
Is MoDOT purchasing property from landowners?
Yes, MoDOT will be not purchase right-of-way and temporary easements.
Will there be a signed detour?
Yes, a signed detour will be in place on local Franklin County roads.
Project Contacts
Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Office: (314)-453-5032
Cell: (314)-565-5648
E-mail: Shirley.Norris@modot.mo.gov
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Office: (314)-453-5032
Cell: (314)-565-5648
E-mail: Shirley.Norris@modot.mo.gov
Contact Photo

Jordan Dalaviras
Title
Area Liaison -- Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Phone: 314-453-5021
Email: jordan.dalaviras@modot.mo.gov
Title
Area Liaison -- Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Phone: 314-453-5021
Email: jordan.dalaviras@modot.mo.gov