Counties Impacted
Iron
Route Impacted
21
Work Type
Curve Improvements
Planning Phase

Project Description

The Missouri Department of Transportation plans to improve Route 21/72 in Iron County. Improvements will extend from Route E near Arcadia, Missouri to Route 49 near Glover, Missouri.

Five curves will be improved along the project limits. The project includes an overlay, adding edgeline rumble stripes, widening four horizontal curves and making improvements to the horizontal curve at Royal Gorge.

Right of Way & Easements

Curves 1, 2, 3, and 5 will require right of way acquisition. A 0.92-acre permanent easement from the Ketcherside Mountain Conservation Area (Missouri Department of Conservation) will be required for curves 2, 3 and 4. In addition, a 1.58-acre permanent easement will be required for curve 5 at Royal Gorge.

Timeline & Traffic

The project is expected to be let in fall 2024, with completion anticipated in fall 2026. A closure of Route 21 at Royal Gorge is planned for a period of 30 to 45 days to complete the rock bluff excavation work. Other areas of Route 21 will consist of flagging operations. 

Image
Aerial Showing Curve 5 for Route 21/72 Project in Iron County

Curve Location Details

Click the link below to view a detailed aerial of each curve location.

Learn More

Curve Locations Map

Embed
Is Responsive
Embed Code

Contact Us

Contact Photo
Pete Berry
Pete Berry
Title
Project Manager
Department
Southeast District
Contact Info

(417) 469-6242

Contact Photo
Chris Crocker
Chris Crocker
Title
Area Engineer
Department
Southeast District
Contact Info

(573) 380-1658