Counties Impacted
Cooper
Route Impacted
O
Work Type
Bridge Deck Replacement
Highway Feature
Moniteau Creek
Planning Phase

Project Summary

The Cooper County Route O bridge over Moniteau Creek was built in 1966 and the bridge deck is in poor condition. The supporting structures of the 241-foot-long bridge are in good condition, but the driving surface - the deck - needs to be replaced.

Project Progress

In Progress
Planning and Design Phase

The Missouri Department of Transportation and a consultant team are designing a project to replace deck of the bridge. The estimated total cost (engineering and construction) for this project is $1,106,000. This cost may change.

The current scope of planned work includes replacing the bridge deck, bridge painting, replacing the roadway approaches to the bridge and placing rock on the slopes adjacent to the bridge.

milestone_icon
Complete
Public Informational Meeting
Question/Comment Period: now-Jan. 12

Public Informational Meeting

An online, virtual public informational meeting will be held through Jan. 12. Downloadable exhibits outline the work being planned.

The public is invited to ask questions of the project team either online or by mail. Comments will also be accepted during this time. Mailed-in questions should be postmarked on or before Jan. 12 and addressed to:

Missouri Department of Transportation

Re: Cooper County Route O Bridge over Moniteau Creek Project

1511 Missouri Boulevard

Jefferson City, MO 65109

Questions may also be asked using the online form below (active through Jan. 9).

Meeting Exhibits

All available exhibits regarding the project to replace the Moniteau Creek Bridge deck rehabilitation project can be viewed using the links below.

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's January 2024 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their February 2024 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work. At this time, no work is expected to begin before March 11, 2024.

 

This project is being let in combination with a bridge rehabilitation project on Cooper County Route 5 at Petite Saline Creek.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

An exact schedule of work will be determined after the contract is awarded. Once construction begins, Route O over Moniteau Creek will be closed for an estimated 90 days. During that time, motorists will need to use an alternate route.

At this time, construction is anticipated to be completed by Dec. 1, 2024.

milestone_icon

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge deck?

Built in 1966, the deck or driving surface of the bridge has deteriorated to the point it needs replaced.

How will the construction affect traffic?

The bridge will be closed to all traffic during construction. The contractor will be allowed up to 90 days for the closure and motorists will need to plan an alternate route.

Why is MoDOT closing the road during construction?

MoDOT strives to be a good steward of taxpayer money. By closing the roadway at the Moniteau Creek Bridge, the contractor will be able to work more efficiently within a shorter construction period, saving taxpayer dollars and reducing the time construction will affect motorists.

What if I have more questions?

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Cooper County Route O over Moniteau Creek Bridge Project on your inquiries.

 

How can I stay updated on the project’s progress?

Sign up for project-specific updates using the form below.

Project News

Webform
Sign Up for Project Updates via Email
*
*