Project Details
In this project, MoDOT will be rebuilding the curve at Route H and 100th St, realigning 100th St. to connect to Route H in the middle of the curve, and realigning Crockett St.
How will this project benefit me?
By re-aligning the intersection, it will improve sight distance and also improve safety for motorists.
What is the time line for this project?
This project is set to begin in the summer of 2022 and be completed by fall of 2022
How will this project impact traffic?
Crews will have to close Route H at 100th Street and detour traffic. It's anticipated that the detour will last approximately two months
What will the project cost? How is this project funded?
The current construction cost estimate is $572,000 and will be funded by MoDOT
For viewing:
-
Construction completed on the Missouri Route H and 100th Street improvement project
MoDOT completed the Missouri Route H and 100th Street improvement project. Crews re-opened Crockett Road at Route H and Route H between Stillhouse Rd. and NE 100th Street. This project included curve reconstruction and intersection improvements. As...