Project Summary

MoDOT will replace aging metal pipe culverts with a new double box culvert structure at the crossing of Route CC at Little Creek. The project area is located south of Leslie. The new culvert will handle a higher capacity of water and reduce the risk of flooding. Guardrails will be added on both approaches of the culvert.

 

COST OF PROJECT

$1.4 million

 

IMPACT TO TRAFFIC

A temporary bypass will be constructed around the Route CC work zone for traffic. The bypass will remain for three months as construction is ongoing.

Project Milestones

Complete
Preliminary Planning
April 2022
milestone_icon
Complete
Right of Way Acquisitions
Fall 2023

A minimum number of private parcels are needed for this project.  MoDOT will contact property owners.

milestone_icon
Complete
Project Advertised
January 2024
milestone_icon
Complete
Contract Awarded
March 2024
milestone_icon
Not Started
Construction Begins
April 2024
milestone_icon

WHO TO CONTACT

Contact Photo
Stephen O'Connor Profile Picture
Stephen O'Connor, P.E.
Title
Area Engineer
Department
St. Louis District
Contact Info

Area Engineer, Franklin & Jefferson County Area 

(314) 453-5021

Stephen.OConnor@modot.mo.gov

Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info

Office: (314)-453-5032

Cell: (314)-565-5648

E-mail: Shirley.Norris@modot.mo.gov