Project Overview

The Callaway County Route BB bridge over Hillers Creek, north of Tebbetts, was built in 1968. The supporting structures of the bridge are in good condition, but the deck of the bridge has deteriorated to the point it needs to be replaced. During the project, the bridge rails will also be brought up to current standards. The bridge will be closed during the project and a signed detour will be in place.

Project Progress

Complete
Planning and Design Phase

A project to replace the deck of the Hillers Creek Bridge was designed by a consultant working with the Missouri Department of Transportation. 

milestone_icon
Complete
Public Informational Meeting
Question/Comment Period: Nov. 8-22, 2023

Public Informational Meeting

An online, virtual public informational meeting was held Nov. 8-22. Downloadable exhibits outlined the work being planned and the proposed detour to be used during construction.

The public was invited to ask questions of the project team either online or by mail. Comments were also be accepted during this time. Mailed-in questions should be postmarked on or before Nov. 22 and addressed to:

Missouri Department of Transportation

Re: Callaway County Route B Bridge over Hillers Creek Project

1511 Missouri Boulevard

Jefferson City, MO 65109

 

Meeting Exhibits

All available exhibits regarding the project to replace the Hillers Creek Bridge deck replacement project can be viewed using the links below.

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

The project was part of MoDOT's January 2024 letting when contractors may submit competitive bids. As part of their February 2024 meeting, the Missouri Highways and Transportation Commission awarded a $517,048 contract for this work to E & C Bridge, LLC.  At that time the contractor was given a Feb. 22, 2024, notice to proceed date - the earliest date they could begin work - and a Dec. 1, 2024, completion date.

milestone_icon
Complete
Project Construction, Traffic Impacts, and Completion

Construction crews closed the bridge the morning of Feb. 26, 2024. The bridge reopened on April 8, 2024. Throughout the closure, a signed detour was in place, directing motorists to use Callaway County Route PP and Missouri Route 94. 

milestone_icon

News and Updates

  • Callaway County Route BB reopens at Hillers Creek

    04/09/2024

    JEFFERSON CITY, Mo – The Hillers Creek Bridge on Route BB in Callaway County is now open. Construction crews completed rehabilitation work on the 56-year-old bridge and reopened it to all traffic on Monday, April 8, 2024 

    Crews from E & C Bridge...

  • Route BB in Callaway County to close for bridge deck replacement

    02/20/2024

    JEFFERSON CITY, Mo – The Callaway County Route BB bridge over Hillers Creek will close next week for the replacement of the bridge deck. Construction crews, working with the Missouri Department of Transportation, anticipate restricting all access to...

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge deck?

Built in 1968, the deck or driving surface of the bridge has deteriorated to the point it needs replaced.

How will the construction affect traffic?

The bridge will be closed to all traffic during construction. The contractor will be allowed up to 50 days for the closure and motorists will be directed to use a signed detour route over Routes AA, 94 and PP.

Why is MoDOT closing the road during construction?

MoDOT strives to be a good steward of taxpayer money. By closing the roadway at the Hillers Creek Bridge, the contractor will be able to work more efficiently within a shorter construction period, saving taxpayer dollars and reducing the time construction will affect motorists.

Where should I direct further questions?

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Callaway County Route BB over Hillers Creek Bridge Project on your inquiries.

How can I stay updated on the project’s progress?

Sign up for project-specific updates using the form below.

Webform
Sign Up for Project Updates via Email
*
*