Counties Impacted
Jefferson
Route Impacted
AA
Work Type
Pavement Repair

Project Summary

The Missouri Department of Transportation will resurface, make pavement repairs, and  upgrade guardrails to current standards along Route AA in Festus. The Muddy Creek Bridge over Route AA will also undergo rehabilitation.  The upgrades will cover  the entire 4.421 miles of Route AA (see the outlined map below), starting at Route TT at the west end, to the end of state maintenance (railroad tracks) on the east side.   Prior to the start of the project, culvert replacements will be made along the roadway.

Project Milestones

Complete
Culvert Replacements
March - April 2022

MoDOT Crews will replace culverts along the entire length of Jefferson County Route AA near Festus, beginning Friday, March 25.  Replacements, which will occur in sections, will proceed east to west from 8 a.m. to 4 p.m. Tuesday through Friday.  During this time, sections of Route AA will be closed to through traffic.  The first section of the roadway to be closed will begin at its end of state maintenance (railroad tracks) on the east side, to Weaver Rd. Section closures are expected to last two-three days.  All culvert replacements along Route AA are scheduled to be completed by mid-April, pending weather conditions.

Route AA Section Closures and Starting Dates

  • End of State Maintenance (railroad tracks) to Weaver Rd. - Friday, March 25 (complete)
  • Weaver Rd. to Big Hollow Rd. -  Friday, April 1 (complete)
  • Burley Rd. to Shamrock Rd. - Wednesday, April 6 (weather delay to April 19 - complete)
  • Shamrock Rd. to Route TT - Thursday, April 21 (complete)
  • Burley Rd. to Shamrock Rd.  - Tuesday, May 3 (complete)
milestone_icon
Complete
Project Advertised
April 2022
milestone_icon
Complete
Contract Awarded
June 2022
milestone_icon
Complete
Construction Begins
July 2022
milestone_icon
Complete
Project Completed
November 2022
milestone_icon

IMPACT TO TRAFFIC

There will be flaggers and signs directing motorists through work zones.

 

WHAT IS THE COST OF THE PROJECT?

The estimated cost of the project is $825,000

WHO TO CONTACT

Contact Photo
Stephen O'Connor Profile Picture
Stephen O'Connor, P.E.
Title
Area Engineer
Department
St. Louis District
Contact Info

Area Engineer, Franklin & Jefferson County Area 

(314) 453-5021

Stephen.OConnor@modot.mo.gov

Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info

Office: (314)-453-5032

Cell: (314)-565-5648

E-mail: Shirley.Norris@modot.mo.gov