This project replaced the driving surface (bridge deck) on Route 76 bridge over Table Rock Lake in Cape Fair.  Replaced bridge railings and installed new guardrail at bridge ends.

Missouri Route 76/Table Rock Lake Bridge OPEN to Traffic In Cape Fair on Tuesday, May 18

 

Project Updates/Traffic Alerts

Project Facts:

  • Replace driving surface (bridge deck) on Route 76 bridge over Table Rock Lake in Cape Fair
  • Replace bridge railings
  • Install new guardrail at bridge ends

Construction: September 2020-May 2021 

Estimated total project cost: $2.4 million

Bridge Facts:

  • Built in 1957
  • Carries 4,048 vehicles a day
  • Current bridge deck in need of frequent repairs
  • Route 76/Table Rock bridge rehab project will be combined with the Route 248/Railey Creek bridge replacement. (Work on bridges will NOT take place at the same time.)

Traffic Impacts:

  • One-lane traffic with temporary traffic signals during daytime hours
  • Bridge CLOSED at night. Work hours: 6 p.m. to 6 a.m.