The plan for the Route 61/67 over Joachim Creek bridge project is to replace the old bridge over Joachim Creek. Since the new bridge will be constructed west of the existing bridge, motorists will use existing Route 61/67 until the new bridge is completed at which time traffic will be moved onto the new structure and the old bridge will be demolished.  Some work may also be performed during nighttime hours.

 

Counties Impacted
Jefferson
Project Status
In Progress
Route Impacted
U.S. Route 61
U.S. Route 67

Project Timeline

Complete
Virtual Public Meeting
August 2020
Not Started
Right of Way Acquisitions
Late Winter 2021
Contract Award

February 2022

Construction begins

Spring 2022

Not Started
Construction complete

Spring 2023

What is being done?

MoDOT will be replacing the aging bridge over Joachim Creek. The current bridge was built in 1933 and is long overdue for an upgrade and replacement. The new bridge will be located to the west of the current bridge. The bridge will be wider to accommodate the exiting Mississippi River Trail and the roadway elevation will be raised to reduce the frequency of roadway closures due to flooding. 

What is the total cost of the project?

The total cost of the project is $8.4 million. 

Is MoDOT purchasing property from land owners?

MoDOT will need to purchase some property and/or obtain temporary easements in order to construct the new bridge through the project limits. A Right of Way representative will be contacting affected landowners in the spring of 2021 to begin the acquisition process. 

Right of Way Guidelines 

What if I have questions?

Please contact Project Manager Shirley Norris at 314-565-5648, Monday through Friday 7:30 a.m. to 4 p.m.

Frequently Asked Questions