Counties Impacted
Sullivan
Project Status
In Progress

Current Proposed Timeline

Complete
Design and Public Input Phase
Complete
Contractors Bid on Project

The project was let in October 2018 allowing contractors to submit competitive bids for both projects. The projects were let in combination, meaning the contractor submitted one bid for the total cost of both projects.

Complete
Contract Awarded

The Missouri Highways and Transportation Commission reviewed the bids and awarded the bid to Widel, Inc. at their October 2018 meeting.

In Progress
Contracts Begin Work
The contractor is allowed per contract to begin work December 2018. The bridge is currently closed to all traffic as the contractor works to replace the bridge. Reopening of the bridge was planned for mid-March, but due to winter weather and freezing temperatures has been extended to early April.
Not Started
Completion Date

The contract completion date is currently set for August 1, 2019. The contractor may complete their work prior to that date, if conditions allow. The contractor hopes  to have work completed by early April.

News

  • UPDATE: Sullivan County Newtown Branch Bridge Replacement

    02/28/2019

    MILAN, Mo. – Contractors from Widel, Inc., working with the Missouri Department of Transportation, closed the Route 139 Newtown Branch Bridge for a replacement project in January. Consistent winter precipitation and freezing temperatures have delayed...

Old Bridge

Built in 1933 Structurally deficient Guardrail not up to standards 78' long 20' wide Carries 400 cars per day Striped as one-lane bridge

Proposed New Bridge

Up to current standards Upgraded guardrail 87' long Will be nearly 28-feet wide with 12-foot lanes Will be restored to two lanes

Frequently Asked Questions

 

Q: Why will the road be closed during construction? And for how long?

A: Closing the roadway to all traffic saves taxpayer money by allowing the contractor to work more safely and efficiently. This will result in a shorter overall construction period. The road could be closed up to four months by contract.

 

Q: What is the current planned detour?

A: At this time there is no plan to sign a detour around he closure. Traffic control and signing will be in place to alert motorists to seek an alternate route.

 

Q: Why not build a bypass?

A: Based on the cost/benefit ratio, building a bypass would not be a good use of taxpayer funds.

 

Q: Will you have to acquire any right of way?

A: No new right of way will be needed and existing utilities will not be affected by this project.

 

Q: Who can I contact if I have further questions?

A: Questions about the project may be directed to Project Manager Joyce Reynolds

 

Q: How can I stay updated on the projects progress?

A: Sign up for project-specific updates below:

Webform
Contact Form
*
*
*
*