Milestones

Image
Rocheport Groundbreaking Hardhat and Beam

Project Groundbreaking

October 12, 2021

Governor Mike Parson and Missouri Department of Transportation officials were joined by federal, state, and local leaders to commence construction of the new Interstate 70 Missouri River bridges near Rocheport.

Press Release | Photos

Watch a video of the ceremony
Image
Rocheport Project Logo

Virtual Public Meeting

September 23, 2021

A virtual open house was held on Thursday, September 23 from 5:30-7 p.m. to discuss the construction of the new Interstate 70 Missouri River bridge near Rocheport. MoDOT staff and representatives from the Lunda Team, the design-build contractor, will review the project timeline and provide more details on the design and construction of the bridge. 

Watch the Presentation
Image
Rocheport Project Logo

Design-Build Team Selected By MHTC

July 1, 2021

On July 1, 2021, the Missouri Highways and Transportation Commission announced the selection of the Lunda Team, made up of Lunda Construction Co., Parsons Transportation Group, Inc., Dan Brown & Associates, and Hugh Zeng United, as the design-build contractor to replace the Interstate 70 Missouri River Bridge near Rocheport.

The winning proposal showed not only an understanding of the engineering endeavor set out before the teams and a design that will serve travelers for the next century, it also showed an understanding of the local, statewide, and national importance of the work.

The design includes two bridges, one in each direction of travel, each with three lanes. This allows for construction to take place with a limited impact to traffic.

Read the full press release
Image
Rocheport Project Logo

Shortlist of Potential Project Contractors Announced

March 2, 2021

Following an extensive evaluation process, four qualified teams have been selected to compete for the contract to design and construct a new Missouri River Bridge on Interstate 70 near Rocheport.

The Missouri Department of Transportation has received Statements of Qualification from potential design-build teams for the Rocheport Bridge project. Four 

“We are very pleased with the interest we received in working on the Rocheport Bridge project. The four short-listed teams are all very experienced and capable of producing a successful project,” said Project Director Brandi Baldwin. “We look forward to moving forward in the process and selecting the final design-build team.”

The following teams (in no particular order) were selected to further develop their proposals on the project:

  • Traylor-Ames Joint Venture Team - Traylor Brothers, Inc.; Jacobs Engineering Group, Inc.; Ames Construction, Inc.
  • American Bridge/Garver Team - American Bridge Company; Garver, LLC; Hg Consult, Inc.; Terracon
  • Rocheport Bridge Constructors - Massman Construction Company; HNTB Corporation; Emery Sapp & Sons, Inc.
  • Lunda Team - Lunda Construction Co.; Parsons Transportation Group, Inc.; Dan Brown & Associates; Hugh Zeng United
Read the full press release
Image
Rocheport Project Logo

RFQ Issued & Virtual Industry Meeting

January 29, 2021

A draft RFP is still available. Any consultant or contractor may request access to these resources by contacting the Rocheport Design-Build Team.  

Attendance list for the Virtual Attendance Meeting

Industry Meeting Presentation

 

Industry Meeting Presentation
Image
Rocheport Project Logo

Virtual Open House

January 26, 2021

A virtual open house was held on Tuesday, Jan. 26 from 5 p.m. to 6:30 p.m. to discuss the construction of the new Interstate 70 Missouri River bridge near Rocheport. MoDOT staff went over the scope of the project, as well as the timeline and goals. No design work has been done. That will be completed by the team that is retained to design and construct the project. 

See the open house presentation
Image
SST Schedule

Early Release Information Provided to Consultants and Contractors

June 2020

In anticipation of procurement in early 2021, MoDOT prepared Early Release Information for all consultants and contractors interested in pursuing the design-build contract. 

Image
I-70 Rocheport Bridge in Cooper County

Geological Testing

March 2020

As part of preparations for the construction of the new bridge, contractors for the Missouri Department of Transportation gathered geo-technical data and survey information. The tests, which involve drilling holes beneath the surface, will provide valuable information about the area’s rock and soil stability.

Image
Rocheport October 2019 Event

Project Kick-Off Event

October 2019

Several local, state and national leaders gathered at Les Bourgeois Blufftop Bistro on October 2 to discuss the upcoming replacement of the Interstate 70 Missouri River Bridge near Rocheport. Governor Mike Parson was introduced by MoDOT Director Patrick McKenna. He was joined by Senator Roy Blunt, Missouri State Senator Caleb Rowden, Missouri State Representative Chuck Basye, Columbia Mayor Brian Treece and Boone County Presiding Commissioner Dan Atwell.

Event Photos

View the video here
Image
I-70 Rocheport Bridge in Cooper County

Re-Evaluation of Environmental Study

December 2019

This process is part of the National Environmental Policy Act 2005 Finding of No Significant Impact for the Second Tier Final Environmental Assessment and Final Section 4(f) Evaluation of Section of Independent Utility 3 for the replacement of the I-70 Missouri River Bridge at Rocheport.

Click here to see the full public notice
Image
SST Schedule

Missouri Receives $81.2 million INFRA Grant

July 2019

The $81.2 million Infrastructure for Rebuilding America (INFRA) grant from the U.S. Department of Transportation enables a $240 million project to replace the existing four-lane I-70 bridge with a six-lane structure built just to the south of the current location, as well as reconstruct the Route BB interchange just east of the bridge. 

Read the full press release from Governor Parson here