Districts Impacted
Project Summary
The Missouri Department of Transportation plans to rehabilitate the U.S. Route 63 bridge over Little Piney Creek. The bridge deck has deteriorated to the point of needing replacement, but the supporting structures are in good condition. The bridge will have a new deck and concrete barriers installed, along with replacing the existing guardrail.
Little Piney Creek Bridge
- Built in 1967.
- Length: 343 feet. Width: 32 feet.
Project Progress
The Missouri Department of Transportation is in the process of designing a new bridge deck U.S. Route 63 over Little Piney Creek. Along with the redeck, the project includes replacing pavement markings and upgrading barriers.
This project is not expected to require any new right-of-way acquisition.
This project was included in MoDOT’s March 2025 letting. The original low bidder was declared non-responsive, so the contract was awarded $1,560,000 to Kozney-Wagner, Inc., the second-lowest bidder. Because of the delay in awarding the contract, Kozney-Wagner was unable to complete the work within the originally planned timeframe.
The notice to proceed is May 5, 2026, but the exact schedule of work and planned start date are not yet known.
At this time, construction is anticipated to begin as early as May 2026. Construction is expected to take approximately 150 calendar days, subject to change.
The roadway is expected to stay open during construction with signals in place to direct traffic.
At this time, the new bridge deck is expected to be completed by Dec. 1, 2026.
Bridge Location
Current Condition
Frequently Asked Questions
Why is MoDOT replacing the bridge deck?
The existing U.S. Route 63 bridge over Little Piney Creek was built in 1967. The deck is in poor condition and needs to be replaced. The bridge barriers and guardrail also need to be upgraded. The new bridge deck, barriers and rail will improve the drivability and safety for motorists and extend the life of the bridge.
How will traffic be impacted?
At this time, construction is anticipated to begin as early as May 2026. Construction is expected to take approximately 150 calendar days, subject to change.
The roadway is expected to stay open during construction with signals in place to direct traffic.
What factors contributed to the delay in starting the project?
This project was included in MoDOT’s March 2025 letting. The original low bidder was declared non-responsive, so the contract was awarded $1,560,000 to Kozney-Wagner, Inc., the second-lowest bidder. Because of the delay in awarding the contract, Kozney-Wagner was unable to complete the work within the originally planned timeframe.
The notice to proceed is May 5, 2026, but the exact schedule of work and planned start date are not yet known.
What is the expected completion date for this project?
At this time, the new bridge deck is expected to be completed by Dec. 1, 2026.
What if I have more questions?
You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Phelps U.S. Route 63 Little Piney Creek Bridge Rehabilitation on your inquiries.
How can I stay updated on the project’s progress?
Sign up for project-specific updates using the form below.