Counties Impacted
Johnson
Route Impacted
50
Work Type
Bridge Rehabilitation
Additional Work Types
Bridge Rehabilitation
Planning Phase

news Project Summary

This project includes bridge rehabilitations on U.S. Route 50 westbound over Devils Branch and Post Oak Creek. These bridges are located 0.6 miles west of County Road 105 and 0.7 miles east of NW 191 Rd west of Warrensburg. The project is scheduled to begin in Summer 2027.

Project Milestones

In Progress
Planning Phase
2026 - Spring 2027
milestone_icon
Not Started
Public Meeting
September 24, 2026 from 4:30pm-6:30pm
Warrensburg Municipal Building
104 S Holden St, Warrensburg, MO 64093
milestone_icon
Not Started
Construction
Summer 2027 - Fall 2027
milestone_icon

Public Meetings

IN PERSON
MEETING DATE AND TIME
09/24/2026 AT 4:30pm–6:30pm
COMMENT PERIOD
09/24/2026–10/08/2026

JOHNSON COUNTY – The Missouri Department of Transportation will host a public meeting regarding bridge rehabilitation work on U.S. Route 50 westbound over Post Oak Creek and Devils Branch west of Warrensburg. The meeting will take place on Thursday, Sept. 24 from 4:30 p.m. to 6:30 p.m. at the Warrensburg Municipal Building located at 104 S Holden St., Warrensburg, MO 64093.

Please note that this is an open-house-style meeting and NO formal presentations will be made. Those interested can attend the hearing anytime between the advertised hours to ask questions, learn more about the project, and leave comments. There will also be an option to leave comments online beginning at 4:00 p.m. on Thursday, Sept. 24 until 11:59 p.m. on Thursday, Oct. 8. The online commenting period will be available on the project page: U.S. Route 50 Bridge Rehabilitations near Warrensburg in Johnson County | Missouri Department of Transportation

MoDOT is committed to providing access to this event for all participants. If you need a reasonable accommodation or translation services, please contact Kansas City District Communications at kccr@modot.mo.gov by Wednesday, Sept. 16.

For those unable to attend the meeting or access the project online, project materials are available by request at the MoDOT district office located at 600 NE Colbern Rd. in Lee’s Summit, MO. Customers may contact Project Manager Claudia Hoffman at claudia.hoffman@modot.mo.gov

For more information about MoDOT news, projects or events, please visit our website at www.modot.mo.gov/kansascity. For instant updates, Follow MoDOT_KC on X, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for work zone updates or call 888-ASK-MODOT (275-6636).

Route Impacted
50
Cities Impacted
Warrensburg
Counties Impacted
Johnson

Latest News

FREQUENTLY ASKED QUESTIONS

Why is this project happening?

While the integrity of the bridges remain, the bridge decks require repairs which will be addressed with a full redeck.

What will be the traffic implications?

Westbound 50 Hwy traffic will be reduced to one lane and utilize temporary crossovers to be put into a head-to-head configuration with eastbound traffic. Eastbound traffic will also be reduced to one lane.

How much will this project cost?

The project is estimated to cost $3.3 million.

destination Project Map

Embed
Is Responsive
Embed Code

worker Project Contacts

Contact Photo
photo
Marisela Ward
Title
Area Representative
Department
Kansas City District
Contact Info

Johnson, Lafayette, Pettis and Saline Counties

816-334-9737

Marisela.Ward@modot.mo.gov

Contact Photo
Headshot of a woman with a dark shirt and a brown background