Districts Impacted
Project Need and Purpose
The intersection of U.S. Route 169 and Buchanan County Route FF was identified for an intersection improvement project that will improve the turning radius for tractor-trailers. The project also will include resurfacing the intersection and extending a culvert near the intersection.
Project Progress
MoDOT's Planning and Design team is designing a project to resurface the intersection and allow more turning room for tractor trailers. MoDOT will contact property owners to obtain the right-of-way and easements required for this project.
A public open house meeting was held on Wednesday, January 22 at the Missouri Department of Transportation's Northwest District Office.
If you were unable to attend the open house, two other opportunities for public comment are available through Wednesday, February 5, 2025.
- Use the comment form below.
- Mail your comments to:
Buchanan Route FF Intersection Improvement Project
Missouri Department of Transportation
3602 North Belt Highway
St. Joseph, MO 64506
All comments must be postmarked by Wednesday, February 5, 2024.
The contract for the intersection improvement project is part of the January 2026 letting for contractor bids. The contract may be awarded by the Missouri Department of Transportation Commission at its February 2026 meeting.
The construction timeline will be determined by MoDOT and the contractor after the contract is awarded.
Frequently Asked Questions:
Q: Will the road be closed during construction?
A: During construction, U.S. 169, Route FF and 49th Street will be closed during a portion of the project.
Q: Will there be a planned detour for this project?
A: There is no signed detour planned for this project.
Q: Is right-of-way required for this project?
A: Yes, some right-of-way will be required for this project. MoDOT will work with property owners to determine the right-of-way and reach an agreement ahead of the project's construction.
Q: How can I stay updated on the project's progress?
A: Sign up for project-specific updates using the form below.
Project News
-
Reminder: Buchanan County I-229 Double Decker bridge to close beginning Aug. 25
ST. JOSEPH, Mo. – The Buchanan County Interstate 229 Double Decker bridge in St. Joseph is scheduled to close beginning Monday, Aug. 25. Crews from the Missouri Department of Transportation will complete annual maintenance of the bridge, signage, and...
-
Buchanan County Route 59 and Alabama Street project update
ST. JOSEPH, Mo. – The intersection improvement project on U.S. Route 59 and Missouri Route 752 (Alabama Street) in St. Joseph recently experienced delays due to concerns with the existing subgrade, the ground beneath the roadway, on Alabama Street...

Need More Information?
We're here to help! If you're looking for additional information, you can contact us at:
- nwcr@modot.mo.gov
- 1-888-ASK-MODOT (275-6636) - reference Buchanan County U.S. Route 59 Intersection Improvement Project