Counties Impacted
Jefferson
Route Impacted
61
67
Work Type
Two-Way Left Turn Lane (TWLTL) Construction

PROJECT SUMMARY

To maintain the roadway and continue to keep motorists safe, improvements need to be made on Route 61/67 in Jefferson County from approximately Brandon Wallace Way to 6th/8th Street in Crystal City.

MoDOT plans to add a two-way left turn lane, address existing drainage issues, and resurface the pavement in the area. The existing curbs, pipes, and inlets have outlived their intended functions. Curbs will be updated, drainage pipes will be replaced where needed, and inlets and drains will be cleaned out. The installation of a two-way left turn lane will provide safer left turn access to the businesses along this section of Route 61/67 in Crystal City.

Project Schedule

Complete
Right-of-Way Property Acquisition
Spring 2024
milestone_icon
Complete
Project Advertised
May 2025
milestone_icon
Complete
Letting Date
June 2025
milestone_icon
Complete
Contract Award
July 2025
milestone_icon
In Progress
Construction Begins
June 2026

Notice to Proceed 

milestone_icon

Frequently Asked Questions

Why is MoDOT temporary reducing lanes from this area?

Currently, there are two lanes in each direction, northbound and southbound. During construction, MoDOT will shift over traffic to allow one northbound and southbound lane and add a temporary center turn lane. Once construction is complete, there will be two northbound and two southbound lanes again, with a permanently added center turn lane (TWLTL).

Why did work start on this area on Route 61/67 with the Interstate 55 Corridor Upgrades project still under construction?

This project was not allowed to begin until the southern limits of the I-55 project were completed. As the southern part of the I-55 project is now completed, motorists will see the barrier wall removed and lanes are back to full width.

Will heavy truck loads still be able to pass through?

Some heavy trucks will still be permitted, provided they meet all oversize/overweight permit requirements. The work zone specifics are shared with MoDOT's multimodal department, which works directly with the oversized and overweight trucks.  These trucks receive permits specifying the routes they must take to reach their destination.  With the specifics of the work zone, and with our multimodal department working with each permit, they will be able to determine if that truck is unfit to travel through.  

Will the local businesses along this route will customers still be able to access?

While this project was not allowed to begin until the Southern section of the I-55 project was completed, our Right-of-Way (land) Department works with the affected businesses along the corridor.  Access to entrances along the corridor will be maintained to keep access open during the project.  If there are any businesses that are concerned or would like to speak with us, we are happy to speak with them.  

Is this project a part of the Interstate 55 Corridor Upgrades?

Adding the turn lane is not part of the I-55 Corridor Upgrades; this is a separate project that addresses safety concerns by adding a two-way left-turn lane, replacing drainage structures, and addressing aging pavement.  Adding a two-way left-turn lane provides safety benefits by reducing crashes, with a heavy focus on rear-end crashes. This project cost $3.98 million. 

How much will the project cost?

Construction cost is estimated at $3.98 million.

 

What is the expected construction complete date?

The expected completion of the project is Spring 2027.
 

What if I have questions?

Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info

Office: (314)-453-5032

Cell: (314)-565-5648

E-mail: Shirley.Norris@modot.mo.gov

Contact Photo
Jordan Dalaviras
Jordan Dalaviras
Title
Area Liaison -- Franklin and Jefferson Counties
Department
St. Louis District
Contact Info

Phone: 314-453-5021
Email: jordan.dalaviras@modot.mo.gov