Districts Impacted
Counties Impacted
Franklin
Route Impacted
PP
30
Work Type
Pavement Resurfacing
Planning Phase
Project Summary
The Missouri Department of Transportation will work on pavement resurfacing, pipe replacement, upgrade guardrail and replace signage from Route 30 to Pickles Ford Road, including culvert replacement over the Meramec River and a culvert extension over Hoosier Creek.
Project Milestones
Not Started
Project Advertised
December 2025
Not Started
Project Letting Date
January 2026
Not Started
Project Award Date
February 2026
Not Started
Anticipated Notice to Proceed
March 2026
Frequently Asked Questions
What is the estimated cost of construction?
The estimated cost of construction is $3.05 million.
Is MoDOT purchasing property from landowners?
Yes, MoDOT will be purchasing some right-of-way and temporary easements.
Project Contacts
Shirley Norris
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Office: (314)-453-5032
Cell: (314)-565-5648
E-mail: Shirley.Norris@modot.mo.gov
Title
Project Manager, Franklin and Jefferson Counties
Department
St. Louis District
Contact Info
Office: (314)-453-5032
Cell: (314)-565-5648
E-mail: Shirley.Norris@modot.mo.gov
Contact Photo

Jordan Dalaviras
Title
Area Liaison, Franklin and Jefferson County
Department
St. Louis District
Contact Info
Phone: (314) 453-5021
E-mail: jordan.dalaviras@modot.mo.gov
Title
Area Liaison, Franklin and Jefferson County
Department
St. Louis District
Contact Info
Phone: (314) 453-5021
E-mail: jordan.dalaviras@modot.mo.gov