stoplight Project Summary

MoDOT plans to improve two intersections in Poplar Bluff, Missouri. The updates include removing the signals at the intersection of Route WW and Henry Street and replacing the signals at the intersection of Business 60 and 9th Street. 

Project Timeline

Online Meeting/Comment Period
Sept. 22 - Oct. 13, 2026
milestone_icon
Tentative Letting
December 2027
milestone_icon
Construction Begins
As early as February 2028
milestone_icon
Construction
Approximately 3 months
milestone_icon
Webform

SHARE YOUR THOUGHTS!
Upcoming Signal Updates in Poplar Bluff, MO

The Missouri Department of Transportation plans to improve two intersections in Poplar Bluff, Missouri. The updates include removing the signals at the intersection of Route WW and Henry Street and replacing the signals at the intersection of Business 60 and 9th Street. 

  • Signal Removal at Route WW and Henry Street Since the initial installation of traffic signals in this location, traffic volumes have declined. This location does not currently meet criteria for a traffic signal. The project will remove the existing span wire signals and permanently install Rectangular Rapid Flashing Beacons (RRFBs) for the pedestrian crossing. The improvements will also include widening the curve radius at each corner and providing pedestrian refuge islands. 
  • Signal Replacement at Business 60 and 9th Street The existing signal equipment is around 40 years old. In an effort to replace aging infrastructure, the existing signal equipment will be replaced with an updated traffic signal. In addition, the project will add a left turn lane on Business 60 and pedestrian refuge islands on the south side of the intersection. 

Tentatively, the projects will be let in December 2027, with construction beginning as early as February 2028. Construction will be underway for approximately three months at each location. During work, motorists should anticipate potential lane closures and minor delays. 

View the Location Maps > 

Please share your thoughts by submitting the form below by Tuesday, Oct. 13, 2026. Your comments will be sent directly to the project team. 

*
*
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

news Contacts

Contact Photo
Seiji Shimbo_SE_Project Manager
Seiji Shimbo
Title
Project Manager
Department
Southeast District
Contact Info

(573) 472-5389