Districts Impacted
Counties Impacted
Iron
Route Impacted
U
Work Type
Bridge Replacement
Planning Phase
Project Summary
The Missouri Department of Transportation plans to replace the Route U bridge over Logan Creek in Iron County. The bridge is located between County Road 28 and Logan Road, east of Belleview, Missouri.
Project Timeline
In Progress
Online Meeting/Comment Period
Oct. 29 - Nov. 19, 2026
Tentative Letting
Dec. 2028
Construction Begins
As early as Feb. 2029
Anticipated Completion
Approximately 3 months following the start of construction
Webform
For More Information
Contact Photo
Seiji Shimbo
Title
Project Manager
Department
Southeast District
Contact Info
(573) 472-5389
Title
Project Manager
Department
Southeast District
Contact Info
(573) 472-5389