news Project Summary

MoDOT plans to replace the Route OO bridge over the Whitewater River in Cape Girardeau County. The bridge is located four miles south of Burfordville, Missouri between County Road 379 and County Road 365. The new bridge will be 26 feet wide, six feet wider than the existing structure.


 

Project Timeline

Online Meeting/Comment Period
Sept. 16 - Oct. 7, 2025
milestone_icon
Tentative Letting
Spring 2026
milestone_icon
Construction Begins
Oct. 19, 2026, weather permitting
milestone_icon
Completion Anticipated
May 1, 2027, weather permitting
milestone_icon

caution Construction Update: Oct. 19, 2026 - May 1, 2027, weather permitting

Route OO in Cape Girardeau County will be closed as construction crews replace the bridge over Upper Whitewater Creek. This section of roadway is located from County Road 365 to County Road 379. Weather permitting, work is scheduled to begin Monday, Oct. 19 with completion anticipated Saturday, May 1, 2027. A signed detour will be in place.

View the Location Map > 

Route OO Whitewater River Bridge Replacement: Detour Map