Counties Impacted
Callaway
Route Impacted
H
Work Type
Bridge Deck Replacement
Highway Feature
Middle River
Planning Phase

The Callaway County Route H bridge over the Middle River is slated for rehabilitation work in 2026. Built in 1964, the supporting structure is in good condition, but the driving surface has deteriorated and needs to be replaced. 

The proposed traffic control plans for construction calls for closing Route H with a signed detour throughout the bridge deck replacement.

PROJECT PROGRESS

In Progress
Planning and Design Phase

The Missouri Department of Transportation is in the process of designing a new bridge deck. The plans for the new deck, which will be the same width as the existing structure, include new approach pavement and installing new guardrail.

This project is not expected to require any new right-of-way acquisition. 

The estimated total cost (engineering and construction) for this project is $683,000. This cost may change.

milestone_icon
Complete
Public Input
May 22 – June 12, 2025

During the three-week comment period running May 22 – June 12, 2025, the community and interested parties had multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts. 

  1. In-person - An open-house style public meeting was held Thursday, May 29, 2025, from 4:30 to 6 p.m. at the Carrington Baptist Church located at 3301 State Hwy H, Fulton. The project team was on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.
  2. Online - All meeting exhibits are available on this website, and feedback may be submitted using the form below through June 12, 2025.
  3. By email – Send comments through June 12, 2025, to CDCR@modot.mo.gov with the subject line: Route H Bridge Deck Replacement over Middle River in Callaway County.
  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by June 12, 2025. Please reference: Route H Bridge Deck Replacement over Middle River in Callaway County.
milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's March 2026 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their April 2026 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction is expected to take place in 2026. 

The proposed traffic control plans for construction call for closing Route H with a signed detour.

milestone_icon
Not Started
Project Completion

At this time, the new bridge deck is expected to be complete by Dec. 1, 2026.

milestone_icon

Meeting Materials

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge deck?

Originally built in 1964, the supporting structures are in good condition, but the driving surface has deteriorated and needs to be replaced.

The proposed traffic control plans for construction call for closing Route H with a signed detour.

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Route H Bridge Deck Replacement over Middle River in Callaway County on your inquiries.

Sign up for project-specific updates using the form below.