Project Summary
The Missouri Department of Transportation plans to rehabilitate the Route EE bridge over Cane Creek Overflow in Butler County. The bridge is located between County Road 269 and County Road 267, southeast of Neelyville, Missouri. The project includes replacing the bridge deck.
Project Timeline
Tentative Letting
Nov. 2027
Construction Begins
As early as Jan. 2028
Anticipated Completion
3 months following the start of construction