Project Summary

The Phelps County Route BB bridge in Rolla over Oak Street, Olive Street, and BNSF Railway, was built in 1974. While the supporting structures are in good condition, the bridge deck - or driving surface - is in need of repairs. The project will include repairing the bridge deck as well as adding new approach pavement and pavement markings.  

Project Progress

Complete
Planning and Design Phase

The Missouri Department of Transportation and its consultant have designed new improvements to extend the functional life of the bridge.  

The estimated total cost, including engineering and construction, is $3.2 million. This cost may change.  

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

This project was part of MoDOT's January 2026 letting when contractors submitted competitive bids. The Missouri Highways and Transportation Commission awarded the contract as part of their February 2026 meeting. The $1,676,851 contract was awarded to Concrete Strategies, LLC. 

 

milestone_icon
Not Started
Project Construction and Traffic Impacts

The notice to proceed is March 6, 2026, but the exact schedule of work and planned start date are not yet known. Work is expected to take 104 days, subject to change.  

The Route BB bridge is expected to remain open, with construction staged to only close half of the bridge at a time. For motorists' safety while work is occurring overhead, Oak Street and Olive Street below the bridge will be closed during construction, with traffic directed to use surrounding local roadways. 

milestone_icon
Not Started
Project Completion

At this time, the project is expected to be completed by Dec. 1, 2026. 

milestone_icon

FREQUENTLY ASKED QUESTIONS  

Why is MoDOT replacing the bridge? 

Built in 1974, the deck is in need of repairs. The project consists of repairing the bridge deck as well as adding new approach pavement and pavement markings. 

How will this bridge work affect traffic? 

Construction is expected to take place in 2026.  

The Route BB bridge is expected to remain open, with construction staged to only close half of the bridge at a time. For motorists’ safety while work is taking place overhead, Oak Street and Olive Street below the bridge will be closed during construction, with traffic directed to use surrounding local roadways. Work is expected to take 104 days, subject to change. 

What is the expected completion date for this project? 

At this time, the project is expected to be completed by Dec. 1, 2026. 

What if I have further questions?  

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Route BB Bridge Rehabilitation over Oak Street, Olive Street, & BNSF Railway in Phelps County on your inquiries. 

How can I stay updated on the project’s progress? 

Sign up for project-specific updates using the form below. 

Project News

  • I-44 westbound off-ramp at Exit 172 to close at noon today

    03/24/2026

    JEFFERSON CITY, Mo. – A towing company plans to begin the removal of a vehicle, its contents, and debris following a recent crash on Interstate 44 near Exit 172. The removal will take place over several days and is scheduled to begin at noon today...

  • Bridge work starts this week on Kingshighway in Rolla

    03/23/2026

    JEFFERSON CITY, Mo. – Contractors have resumed rehabilitation work on several bridges over Interstate 44 in Phelps County with one complete, one underway and work beginning on the third this week.

    As early as today, Monday, March 23, work to...

  • Planned Road Work for Mid-Missouri

    03/20/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area March 23-29, 2026. Weather conditions may postpone scheduled work. Many projects will include lane closures which...

  • Planned Road Work for Mid-Missouri

    03/13/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area March 16 – 22, 2026. Weather conditions may postpone scheduled work. Many projects will include lane closures which...

Webform
Sign Up for Project Updates via Email
*
*
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.