Counties Impacted
Phelps
Route Impacted
BB
Work Type
Bridge Rehabilitation
Highway Feature
BNSF Railway
Planning Phase

project Project Summary

The Phelps County Route BB bridge in Rolla over Oak Street, Olive Street, and BNSF Railway, was built in 1974. While the supporting structures are in good condition, the bridge deck - or driving surface - is in need of repairs. The project will include repairing the bridge deck as well as adding new approach pavement and pavement markings.  

Project Progress

Complete
Planning and Design Phase

The Missouri Department of Transportation and its consultant have designed new improvements to extend the functional life of the bridge.  

The estimated total cost, including engineering and construction, is $3.2 million. This cost may change.  

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

This project was part of MoDOT's January 2026 letting when contractors submitted competitive bids. The Missouri Highways and Transportation Commission awarded the contract as part of their February 2026 meeting. The $1,676,851 contract was awarded to Concrete Strategies, LLC. 

 

milestone_icon
Not Started
Project Construction and Traffic Impacts

The notice to proceed is March 6, 2026, but the exact schedule of work and planned start date are not yet known. Work is expected to take 104 days, subject to change.  

The Route BB bridge is expected to remain open, with construction staged to only close half of the bridge at a time. For motorists' safety while work is occurring overhead, Oak Street and Olive Street below the bridge will be closed during construction, with traffic directed to use surrounding local roadways. 

milestone_icon
Not Started
Project Completion

At this time, the project is expected to be completed by Dec. 1, 2026. 

milestone_icon

FREQUENTLY ASKED QUESTIONS  

Why is MoDOT replacing the bridge? 

Built in 1974, the deck is in need of repairs. The project consists of repairing the bridge deck as well as adding new approach pavement and pavement markings. 

How will this bridge work affect traffic? 

Construction is expected to take place in 2026.  

The Route BB bridge is expected to remain open, with construction staged to only close half of the bridge at a time. For motorists’ safety while work is taking place overhead, Oak Street and Olive Street below the bridge will be closed during construction, with traffic directed to use surrounding local roadways. Work is expected to take 104 days, subject to change. 

What is the expected completion date for this project? 

At this time, the project is expected to be completed by Dec. 1, 2026. 

What if I have further questions?  

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Route BB Bridge Rehabilitation over Oak Street, Olive Street, & BNSF Railway in Phelps County on your inquiries. 

How can I stay updated on the project’s progress? 

Sign up for project-specific updates using the form below. 

news Project News

  • Planned Road Work for Mid-Missouri

    06/26/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area June 29 - July 5, 2026.  

    Most routine work zones will stop for the Independence Day holiday, but some long-term work...

  • Sugar Tree Road bridge over I-44 is now open to traffic

    06/25/2026

    JEFFERSON CITY, Mo. – Contractors are making progress on rehabilitation work on several bridges along the Interstate 44 corridor in Phelps and Pulaski counties and were able to open the bridge on Phelps County Road 8490 (Sugar Tree Road) over I-44...

  • New, longer westbound I-44 on-ramp at Exit 159 now open

    06/24/2026

    JEFFERSON CITY, Mo. – A milestone was reached today on the project to improve safety and drivability along the Interstate 44 corridor in Pulaski County: the completion of the new, longer westbound on-ramp at Exit 159. The improved ramp connecting...

  • Planned Road Work for Mid-Missouri

    06/18/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area June 22 - 28, 2026.  

    All Counties 

    In addition to the work listed below, other moving operations such as pothole...

Webform
Sign Up for Project Updates via Email
*
*
How did you hear about this project?
How clearly did the information on the website explain the project?
What is most important to you when considering this project?
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.