Counties Impacted
Laclede
Route Impacted
Outer Road (Interstate 44)
Work Type
Bridge Replacement
Highway Feature
Bear Creek
Planning Phase

Built in 1923 and rehabilitated in 1972, the Outer Road 44 bridge over Bear Creek in Laclede County, is in poor condition, showing signs it has reached the end of its useful life, and in need of replacement. The plans for the new bridge, which will be the same width as the existing structure at 26 feet, include raising the bridge 8 inches to provide additional room for water to flow and installing new guardrail.

Construction of a new bridge will require a full roadway closure. No detour will be signed, but signs located well ahead of the closure will alert motorists to use an alternate route.

PROJECT PROGRESS

Complete
Planning and Design Phase

The Missouri Department of Transportation is in the process of designing a new bridge. Preliminary plans for the new structure:

  • 26 feet wide with two 11-foot lanes and two 2-foot shoulders – the same as the existing bridge.
  • Raise the bridge 8 inches for new girders and to provide additional room for water to flow.
  • New guardrail in line with current standards.

This project is not expected to require any new right of way acquisition.

The estimated total cost (engineering and construction) for this project is $1.6 million. This cost may change.

milestone_icon
Complete
Public Input
Oct. 22 – Nov. 5, 2024

During the two-week comment period that ran Oct. 22 – Nov. 5, 2024, the community and interested parties had multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts. 

  1. Online. All meeting exhibits are available on this website and feedback may be submitted using the form below. 
  2. By email – Send your comments to CDCR@modot.mo.gov with the subject line: OR 44 Bridge Replacement Over Bear Creek Project.
  3. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109. Please reference: OR 44 Bridge Replacement Over Bear Creek Project.
milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's February 2025 letting when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their March 2025 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction is expected to take place in the summer of 2025. The bridge will be fully closed for roughly 15 weeks and no detour will be signed. Signs located well ahead of the closure will alert the nearly 400 motorists who use the bridge on an average day to seek an alternate route.

milestone_icon
Not Started
Project Completion

At this time, the new bridge is expected to be complete by Dec. 1, 2025.

milestone_icon

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge?

Built in 1923 and rehabilitated in 1972, the Outer Road 44 bridge over Bear Creek in Laclede County, is in poor condition, showing signs it has reached the end of its useful life, and in need of replacement. 

Preliminary plans for the new bridge:

  • 26 feet wide with two 11-foot lanes and two 2-foot shoulders – the same as the existing bridge.
  • Raise the bridge 8 inches for new girders and to provide additional room for water to flow.
  • New guardrail in line with current standards. 

The bridge will be fully closed for roughly 15 weeks and no detour will be signed. Signs located well ahead of the closure will alert the nearly 400 motorists who use the bridge on an average day to seek an alternate route. 

MoDOT provides the contractor a date when they may begin work, and a date by which all work must be completed. Within that window, the contractor will be allowed up to 105 calendar days during which the roadway may be closed, or they may be subject to liquidated damages. At this time, the earliest date they could begin work would be in April 2025, with all work to be complete by Dec. 1, 2025 (subject to change).

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference OR 44 Bridge Replacement Over Bear Creek Project on your inquiries.

Sign up for project-specific updates using the form below.