Counties Impacted
Barry
Route Impacted
97
Work Type
Bridge Replacement
Highway Feature
Capps Creek
Planning Phase

PROJECT TIMELINE

Not Started
Virtual (Online) Public Meeting
November 2-16, 2026
milestone_icon
Not Started
Project Out for Bid
December 2026
milestone_icon
Project Awarded to Contractor
January 2027
milestone_icon
Not Started
Tentative Construction Start Date
Spring 2027
milestone_icon
Construction Complete
December 2027
milestone_icon

data Purpose and Need

The Missouri Route 97 bridge over Capps Creek in Barry County was built in 1953 and is in deteriorating condition in need of frequent maintenance.

bridge Project Information

The contractor will demolish the current bridge and replace it with a bridge that is approximately one foot higher, two feet wider and approximately five feet longer than the existing structure.

news NEWS RELEASES

Frequently Asked Questions

How long will Route 97 be closed at the bridge?

The contractor will be given up to four months to have the bridge closed to traffic.

Will there be a signed detour around the closure?

Yes, drivers will be directed along a signed detour using routes 60, 37, B and 97.

Will MoDOT need to acquire additional right-of-way for this project?

No. The new bridge will be built entirely within the available right-of-way.

Will I be able to access my property during construction of the new bridge?

Yes, drivers will be able to access all roads and entrances at either end of the bridge but will not be able to drive through the work zone during construction.

How can I ask a question or leave feedback about this project?

MoDOT will host a virtual (online) public meeting from November 2 to November 16, 2026. During that time, you may return to this website and complete a form found here. You also may send an e-mail to swcr@modot.mo.gov or call us at (417) 895-7600.

Webform
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

caution Project Contacts

Contact Photo
Beth Schaller Portrait
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info

Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120

 

Contact Photo
Ray Cook, Project Manager
Ray Cook
Title
Transportation Project Manager
Department
Design
Contact Info

Southwest District

Email: darrell.cook@modot.mo.gov

Phone: (417) 895-7644