Missouri Route 8 and Washington County Routes O and U Intersection Improvements
The intersection of Missouri Route 8 and Washington County Routes O and U in Potosi will undergo several enhancements in Summer 2020 including traffic signal improvements and the construction of additional turn lanes. Fiber optic installation for traffic signals is also planned for intersections along Routes 8, 21, and E in Potosi.
The contract for this project was approved by the Missouri Highways and Transportation Commission in April, with the low bid awarded to Reinhold Electric, which submitted the low bid of $592,058.
Project Details
When: Work is expected to begin Summer 2020 (Details will be announced via traffic signs, social media, this web page and through local media). The contract specifies all work be completed in 90 days or less.
Cost: $592,058
Work Taking Place: The intersection of Missouri Route 8 and Washington County Routes O and U in Potosi will undergo several enhancements including traffic signal improvements and the construction of additional turn lanes. Fiber optic installation for traffic signals is also planned for intersections along Routes 8, 21, and E in Potosi.
Traffic Impact: On average, 4,400 vehicles use Route 8 at this intersection each day. This project will require lane closures with flaggers guiding traffic through the work zone.
Project Milestones
The Missouri Highways and Transportation Commission awarded the bid in April. Reinhold Electric was awarded the contract, after submitting the low bid of $592,058.
The project is scheduled to begin summer 2020.
Once the contractor starts the work they will have 90 days to complete it.