Counties Impacted
Camden
Route Impacted
7
Work Type
Bridge Deck Replacement
Highway Feature
Sellars Creek
In Progress

Two bridges along Missouri Route 7, between Camden County Route T and the city of Richland, are slated for rehabilitation work in 2026. Both the bridge over Sellars Creek and the bridge over Murphy Creek were built in 1964 and rehabilitated in 1988. While the supporting structures are in good condition, the driving surfaces have deteriorated and need to be replaced. 

The traffic control plans for construction involve closing Route 7 (at different times for each bridge) with a signed detour.

PROJECT PROGRESS

Complete
Planning and Design Phase

The Missouri Department of Transportation is in the process of designing new bridge decks. 

This project is not expected to require any new right of way acquisition. 

The estimated total cost (engineering and construction) for this project is $1.7 million. This cost may change.

milestone_icon
Complete
Public Input
March 20 – April 10, 2025

During the three-week comment period that ran March 20 - April 10, 2025, the community and interested parties had multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts. 

  1. In-person - An open-house style public meeting was held Thursday, March 27, 2025, from 4:30 to 6 p.m. at the Richland City Hall located at 204 E. Washington Ave. The project team was on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.
  2. Online - All meeting exhibits are available on this website and feedback may be submitted using the form below.
  3. By email – Send comments to CDCR@modot.mo.gov with the subject line: Route 7 Bridge Deck Replacements over Sellars Creek and Murphy Creek in Camden County.
  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by April 10, 2025. Please reference: Route 7 Bridge Deck Replacements over Sellars Creek and Murphy Creek in Camden County.
milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

As part of their January 2026 meeting, the Missouri Highways and Transportation Commission awarded a $1,099,994.73 contract for this work to E & C Bridge, LLC.

milestone_icon
In Progress
Project Construction and Traffic Impacts
June 1 - October

Between June 1 and early October, crews will be replacing the bridge decks for Sellars Creek and Murphy Creek. The two bridges will be closed at different times – the bridges cannot be worked on simultaneously.

 During construction, motorists will be directed around the closure via Camden County Routes T and H. 

milestone_icon
Complete
Sellars Creek
Closed June 1 - July 23

On June 1, construction crews closed the Route 7 bridge over Sellars Creek to all traffic to replace the deck (driving surface). The bridge reopened on July 23 - ahead of schedule. 

During construction, motorists were directed around the closure via Camden County Routes T and H. 

milestone_icon
In Progress
Murphy Creek
July 27 - October

On July, construction crews closed the Route 7 bridge over Murphy Creek to all traffic to replace the deck (driving surface). The bridge is anticipated to reopen in October. 

During construction, motorists were directed around the closure via Camden County Routes T and H. 

milestone_icon

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge decks?

Both bridges were built in 1964 and rehabilitated in 1988. While the supporting structures are in good condition, the driving surfaces have deteriorated and need to be replaced.

How will this bridge work affect traffic?

The traffic control plans for construction involve closing Route 7 with a signed detour. 

What if I have further questions?

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Route 7 Bridge Deck Replacements over Sellars Creek and Murphy Creek in Camden County on your inquiries.

How can I stay updated on the project’s progress?

Sign up for project-specific updates using the form below.

news News & Updates

  • Route 7 at Sellars Creek northwest of Richland to close next week

    05/26/2026

    JEFFERSON CITY, Mo – Missouri Route 7, between Camden County Route T and the city of Richland, is set to close next week at Sellars Creek. While the driving surface is being replaced, a signed detour will direct all traffic around the closure.  

    The...

  • Input sought on Route 7 bridge deck replacements near Richland

    03/13/2025

    JEFFERSON CITY, Mo The Missouri Department of Transportation is seeking community input on plans to rehabilitate two bridges along Missouri Route 7, between Camden County Route T and the city of Richland, in 2026. The public's input is essential...

Webform
Sign Up for Project Updates via Email
*
*
How did you hear about this project?
How clearly did the information on the website explain the project?
What is most important to you when considering this project?
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.