Counties Impacted
Howard
Route Impacted
5
Work Type
Bridge Rehabilitation
Highway Feature
Sulphur Creek
Planning Phase

Project Summary

The Missouri Route 5 bridge over Sulphur Creek in Howard County, south of New Franklin, is deteriorating and in need of repair. The structure was built in 1926, and the deck (driving surface) is in poor condition. MoDOT is planning to repair and resurface the aging deck to increase the expected life expectancy of the bridge.

Project Progress

In Progress
Planning, Design, and Right of Way Acquisition Phase

A project to replace the bridge deck is currently being designed by the Missouri Department of Transportation. The estimated total cost for this work, including engineering and construction, is $457,000. This cost may change. 

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

This project was part of MoDOT's October 2025 letting when contractors submitted competitive bids. The Missouri Highways and Transportation Commission awarded the contract as part of their November 2025 meeting. The $6,650,955.26 contract was awarded to Christensen Construction Company. 

The notice to proceed is December 8, 2025, but the exact schedule of work and planned start date are not yet known.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

At this time, construction is anticipated to begin as early as spring 2026 and be complete by Dec. 1, 2026. The roadway is expected to remain open during construction, but one lane will be closed at a time with a temporary signal directing traffic.  

milestone_icon

Location

Google Map
Google Map

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge?

The Missouri Route 5 bridge over Sulphur Creek in Howard County, south of New Franklin, is deteriorating and in need of repair. The structure was built in 1926, and the deck (driving surface) is in poor condition. MoDOT is planning to repair and resurfacing the aging deck to increase the expected life expectancy of the bridge.

The contractor will stage lane closures on the bridge so one lane of traffic is maintained through the completion of the project, with temporary traffic signals. 

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Howard County Missouri Route 5 Sulphur Creek Bridge Project on your inquiries.

Sign up for project-specific updates using the form below.

Webform
Sign Up for Project Updates via Email
*
*