Counties Impacted
Dent
Route Impacted
32
Work Type
Bridge Replacement
Highway Feature
Huzzah Creek
Planning Phase

Project Summary

The Missouri Route 32 bridge over Huzzah Creek in Dent County, southwest of Viburnum, is slated for replacement in 2027. Built in 1931, the bridge is in poor condition, showing signs it has reached the end of its useful life, and in need of replacement. 

With a width of 30 feet, the new structure will be wider than the current bridge, which is 24-feet wide.

Missouri Route 32 is expected to remain open during construction, with a one-lane temporary bypass in place and temporary traffic signals directing motorists through the work zone. 

Image
Thumbnail

Public Meeting

An in-person public meeting will be held on Tuesday, Feb. 10, 2026, at the Boss Assembly of God Church from 4:30 to 6 p.m. Members of the project team will be on hand to provide information and answer questions from the community. There will be no formal presentation, so members of the public can come and go as they please during the advertised hours. By participating and commenting, the public can help MoDOT determine design and construction details to best serve the needs of the roughly 1,200 motorists who use the bridge on an average day while being responsible stewards of available funding.  

Bridge Location

Google Map
Google Map

Project Progress

In Progress
Planning and Design Phase

The Missouri Department of Transportation is in the process of designing a new bridge on Missouri Route 32 bridge over Huzzah Creek in Dent County. The new bridge will be 30 feet wide, 6 feet wider than the current structure. The project also includes new approach pavement, barriers, and guardrail. 

This project is expected to require some new right-of-way acquisition. 

The estimated total cost (right-of-way acquisition, engineering, and construction) for this project is $4.6 million. This cost may change (pending MHTC approval).

milestone_icon
In Progress
Public Input
Jan. 27 – Feb. 17, 2026

During the three-week comment period running Jan. 27 – Feb. 17, 2026, the community and interested parties will have multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts.  

  1. In-person - An open-house-style public meeting will be held Tuesday, Feb. 10, 2026, from 4:30 to 6 p.m. at the Boss Assembly of God Church, located at 22651 E. Highway 32 in Boss. The project team will be on hand to answer questions, provide information, and receive input about the project. Comment forms will be available at the meeting. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours. 

  2. Online - All meeting exhibits are available on this website, and feedback may be submitted using the form below by Feb. 17, 2026.  

  3. By email – Send comments to CDCR@modot.mo.gov by Feb. 17, 2026, with the subject line: Missouri Route 32 Bridge Replacement over Huzzah Creek in Dent County.  

  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by Feb. 17, 2026. Please reference: Missouri Route 32 Bridge Replacement over Huzzah Creek in Dent County. 

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's December 2026 letting, when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their January 2027 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work (pending MHTC approval). 

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction is expected to take approximately 6 months and be completed in 2027. Subject to change.

The roadway is expected to remain open during construction, with a one-lane temporary bypass in place and temporary traffic signals directing motorists through the work zone.

milestone_icon
Not Started
Project Completion

At this time, the new bridge is expected to be completed by Dec. 1, 2027. 

milestone_icon

FREQUENTLY ASKED QUESTIONS  

Why is MoDOT replacing the bridge? 

Built in 1931, the bridge is in poor condition, showing signs it has reached the end of its useful life, and in need of replacement.  

How will this bridge work affect traffic? 

The roadway is expected to remain open during construction, with a one-lane temporary bypass in place and temporary traffic signals directing motorists through the work zone and is expected to take approximately 6 months. Subject to change.

What is the expected completion date for this project? 

At this time, the new bridge is expected to be completed by Dec. 1, 2027. 

What if I have further questions?  

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Missouri Route 32 Bridge Replacement over Huzzah Creek in Dent County on your inquiries. 

How can I stay updated on the project’s progress? 

Sign up for project-specific updates using the form below. 

Project News

  • Planned Road Work for Mid-Missouri

    02/13/2026

    All Counties 

    In addition to the work listed below, other moving operations such as pothole patching, brush cutting, and pavement repairs continue in various locations. Motorists should travel with care and be alert for slow-moving equipment. 

    All...

  • Planned Road Work for Mid-Missouri

    02/06/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Feb. 9 – 15, 2026. Weather conditions may postpone scheduled work. Many projects will include lane closures which...

  • UPDATE: Date and Venue change for Dent County bridge meeting

    02/02/2026

    JEFFERSON CITY, Mo. – The venue and date for the upcoming public meeting in Dent County has changed. The meeting will now be held at the Boss Assembly of God Church on Feb. 10, 2026. 

    The public is invited to attend an open-house style meeting on...

  • Planned Road Work for Mid-Missouri

    01/30/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Feb. 2 – 8, 2026. Weather conditions may postpone scheduled work. Many projects will include lane closures which could...

  • Comment period open for Dent County bridge replacement project

    01/27/2026

    JEFFERSON CITY, Mo. – The Missouri Department of Transportation is seeking community input on a project to replace the Missouri Route 32 bridge over Huzzah Creek in Dent County. Built in 1931, the Huzzah Creek bridge is in poor condition, showing...

Webform
Have Project Questions or Feedback? Use the form below to share your questions, thoughts and comments.
*
*
*

Your email address shared here will not be used for any purpose other than communicating about this project.