Districts Impacted
PROJECT TIMELINE
Ozark Technical College Table Rock Campus
10698 Historic Hwy 165, Hollister, MO 65672
This is a come-and-go style meeting with no formal presentation. If you cannot attend, please review the project information and complete the comment form below by August 25.
Project Information
- Constructing a New Bridge over U.S. Route 65 north of the existing U.S. Route 65 and Missouri Route 265 signalized intersection
- Adding one acceleration lane for Missouri Route 265 to southbound U.S. Route 65
- Remove existing signals and center median at U.S. Route 65 and Missouri Route 265
- Estimated Total Cost: $6.1 million
Traffic Impacts
- Nighttime U.S. Route 65 short-term CLOSURE for bridge beam/girder placement over U.S. Route 65
- Flaggers on Missouri Route 265 to direct traffic during the bridge beam/girder placement
- Carpenter Drive and Cedar Valley Road CLOSED in 15-minute increments as crews connect the roads to the New Missouri Route 265 Bridge over U.S. Route 65
Project Updates
-
MoDOT TRAFFIC ALERT: 22nd Street CLOSED at Night, South of Route CC
Where: 22nd Street CLOSED at Night, South of Route CC in Ozark
When: 9 p.m. Thursday Night, November 12 until 6 a.m. Friday Morning, November 13
What: Crews will install a new pipe crossing as part of Phase 1 of the Christian County Route CC...
-
TRAFFIC ALERT: Route H Bridge Over Goodin Hollow Creek OPEN to Traffic after Replacement Project
Where: McDonald County Route H bridge over Goodin Hollow Creek near Pineville
When: As of 10 a.m., Friday, November 6
Details: The bridge was closed in July to allow contractor crews to replace the existing bridge and replace it with one that is 10...
-
Route 97 North/South of Route 60 to experience closures through Nov. 15 in Barry Co.
Where: Missouri Route 97 between Barry County Farm Road 2025 and U.S. Route 60 near Monett Regional Airport
When: Route 97 SOUTH of Route 60 will remain closed (closed September 17) for up to seven days while crews complete additional work. Route 97...
-
MoDOT TRAFFIC ALERT: Broadway Avenue CLOSED & Grant Avenue OPEN under I-44
Where: In Springfield
- Broadway Avenue CLOSED under I-44
- Grant Avenue OPEN under I-44
When: Beginning Monday, November 16
- Crews will move back and forth between Broadway and Grant Avenue and will close the road as they work. Message boards will...
-
MoDOT TRAFFIC ALERT: Greene Co Route MM & Farm Rd 160 CLOSED at Route MM in Republic
Where/When: In Republic
- Greene County Route MM CLOSED between Farm Road 160 and Haile Street
- Monday, November 16 until Monday, November 30
- Farm Road 160 CLOSED at Route MM
- Monday, November 16 until the roundabout is completed
What: Contractor...
Frequently Asked Questions:
What is the purpose of the new bridge over Route 65?
The new bridge allows access to both the northbound and southbound lanes of U.S. Route 65 without having to cross the center median.
Why is this not becoming an interchange?
Due to current funding levels, MoDOT could not include the ramps needed to create a full interchange. However, the bridge and roadway have been designed to accommodate future ramps if funding becomes available.
Isn’t the Ozark Mountain High Road planned to connect to Route 65 in this area?
Yes, the new bridge will be built along the previously planned right-of-way alignment for the Ozark Mountain High Road. If funding becomes available to construct the High Road’s southern segment, the bridge will be positioned for the High Road to intersect with U.S. 65 at that location.
Will Route 65 be closed during construction?
U.S. Route 65 will remain open for the majority of construction. However, nighttime short-term delays and closures will occur as crews place the bridge beam/girder over U.S. Route 65.
How will the project affect Carpenter Drive and Cedar Valley Road?
Carpenter Drive and Cedar Valley Road will connect to both the new bridge over Route 65 and to Route 265 south of the bridge. Most of the construction will occur away from these outer roads. Traffic impacts on Carpenter Drive and Cedar Valley Road will include brief closures of up to 15 minutes as crews complete work to tie the bridge into the outer roads.
How is this project supposed to improve the safety of the intersection?
This project removes signals on Route 65, allowing northbound and southbound traffic to continue without stopping at red lights. The design also eliminates the risk of a 90-degree collision with high‑speed traffic at the current intersection. By adding acceleration and deceleration lanes on Route 65—where drivers can adjust their speed before merging or turning—the project helps reduce impacts on overall traffic flow.
The last day to leave comments on this project is Tuesday, August 25.
Project Contacts
Beth Schaller
Title
Area Engineer
Department
Southwest District
Contact Info
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Forward 44: Southwest I-44 Improvements Deputy Project Director,
Ozarks Transportation Organization: Greene & Christian Counties
Southwest Missouri Council of Governments: Barry, Christian, Dade, Dallas, Greene, Lawrence, Polk, Stone, Taney, & Webster Counties
Email: Beth.Schaller@modot.mo.gov
Phone: (417) 529-4120
Ray Cook
Title
Transportation Project Manager
Department
Design
Contact Info