Districts Impacted
Project Summary
The Missouri Route 240 bridge over Salt Creek in Howard County, south of Fayette, is slated for replacement in 2027. Built in 1932, the 93-year-old bridge is in fair condition, showing signs it has reached the end of its useful life, and in need of replacement.
Construction of a new bridge will require a full roadway closure. A signed detour will be in place.
Public Meeting
An in-person public meeting will be held on Thursday, March 5, 2026, at the Keller Building from 4:30 to 6 p.m. Members of the project team will be on hand to provide information and answer questions from the community. There will be no formal presentation, so members of the public can come and go as they please during the advertised hours. By participating and commenting, the public can help MoDOT determine what best serves the needs of the roughly 2,700 motorists who use the bridge on an average day while being responsible stewards of available funding.
Meeting Materials
Current Bridge Conditions
Bridge Location
Project Progress
The Missouri Department of Transportation is in the process of designing a new bridge on Missouri Route 240 over Salt Creek. The new bridge will be 26 feet wide, 4 feet wider than the current structure and will be raised 2 feet. The project also includes new guardrail, approach pavement, pavement marking, and barriers.
This project is expected to require some new right-of-way acquisition.
The estimated total cost (right-of-way acquisition, engineering, and construction) for this project is $1.6 million. This cost may change.
During the three-week comment period running Feb. 26 – March 19, 2026, the community and interested parties will have multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts.
-
In-person - An open-house-style public meeting will be held Thursday, March 5, 2026, from 4:30 to 6 p.m. at the Keller Building, located at 600 W. Morrison Street in Fayette. The project team will be on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.
-
Online - All meeting exhibits are available on this website, and feedback may be submitted using the form below by March 19, 2026.
-
By email – Send comments to CDCR@modot.mo.gov by March 19, 2026, with the subject line: Missouri Route 240 Bridge Replacement over Salt Creek in Howard County.
-
By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by March 19, 2026. Please reference: Missouri Route 240 Bridge Replacement over Salt Creek in Howard County.
The project is currently scheduled to be part of MoDOT's December 2026 letting, when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of their January 2027 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.
Construction is expected to take place in 2027. The roadway is expected to be closed for 3 months, subject to change.
Construction of a new bridge will require a full roadway closure. A signed detour will be in place.
At this time, the new bridge deck is expected to be completed and open to traffic by Dec. 1, 2027.
FREQUENTLY ASKED QUESTIONS
Why is MoDOT replacing the bridge?
Built in 1932, the 93-year-old bridge is in fair condition and reaching the end of its usable life.
How will this bridge work affect traffic?
Construction of a new bridge will require a full roadway closure. A signed detour will be in place.
Why not build a bypass?
MoDOT strives to be good stewards of the taxpayer funds entrusted to us. Due to the cost, right of way acquisition and environmental impacts, building a bypass would not be a prudent use of these funds.
What is the expected completion date for this project?
At this time, the new bridge is expected to be completed and open to traffic by Dec. 1, 2027.
What if I have further questions?
You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Missouri Route 240 Bridge Replacement over Salt Creek in Howard County on your inquiries.
How can I stay updated on the project’s progress?
Sign up for project-specific updates using the form below.
Project News
-
Public input sought on Howard County bridge project
JEFFERSON CITY, Mo. – The Missouri Department of Transportation is seeking community input on a project which will replace the Missouri Route 240 bridge over Salt Creek in Howard County, south of Fayette. Built in 1932, the bridge is in fair...
-
Planned Road Work for Mid-Missouri
JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Feb. 23 – March 1, 2026. Weather conditions may postpone scheduled work. Many projects will include lane closures whic...
-
Planned Road Work for Mid-Missouri
All Counties
In addition to the work listed below, other moving operations such as pothole patching, brush cutting, and pavement repairs continue in various locations. Motorists should travel with care and be alert for slow-moving equipment.
All...