Counties Impacted
Dent
Route Impacted
19
Work Type
Bridge Rehabilitation
Highway Feature
Spring Creek
Planning Phase

bridge2 Project Summary

The Missouri Route 19 bridge over Spring Creek in Dent County, just south of Salem, is slated for a deck overlay in 2027. Built in 1986, the bridge’s driving surface has deteriorated and is in need of repair. 

At this time, the plans call for one lane to remain open during construction, with temporary traffic signals to guide motorists through the work zone.

Project Progress

In Progress
Planning and Design Phase

The Missouri Department of Transportation is in the process of planning rehabilitation work to extend the useful life of the Missouri Route 19 bridge over Spring Creek. This work is expected to include: 

  • Replacing driving surface. 

  • Replacing pavement markings. 

  • Milling and replacing the asphalt pavement approaching each end of the bridge. 

This project is not expected to require any new right-of-way acquisition.   

The estimated total cost (engineering and construction) for this project is $191,000, subject to change.   

milestone_icon
In Progress
Public Input
Aug. 17 - Aug. 31, 2026

During the two-week online comment period running Aug. 17 – Aug. 31, 2026, the community and interested parties will have multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts.   

  1. Online - All meeting exhibits are available on this website, and feedback may be submitted using the form below by Aug. 31, 2026.   

  2. By email – Send comments to CDCR@modot.mo.gov by Aug. 31, 2026, with the subject line: Missouri Route 19 Bridge Rehabilitation over Spring Creek in Dent County.   

  3. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by Aug. 31, 2026. Please reference: Missouri Route 19 Bridge Rehabilitation over Spring Creek in Dent County. 

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is currently scheduled to be part of MoDOT's December 2026 letting, when contractors may submit competitive bids. The Missouri Highways and Transportation Commission may award the contract as part of its January 2027 meeting and, if the contract is awarded, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction is expected to take place in 2027.  

At this time, the plans call for one lane to remain open during construction, with temporary traffic signals to guide motorists through the work zone.  

milestone_icon
Not Started
Project Completion

Construction is expected to be complete by Dec. 1, 2027.  

milestone_icon

FREQUENTLY ASKED QUESTIONS   

Why is MoDOT rehabilitating the bridge?  

Built in 1986, the bridge driving surface has deteriorated and is in need of repair.  

How will this bridge work affect traffic?  

At this time, the plans call for one lane to remain open during construction, with temporary traffic signals to guide motorists through the work zone.   

What if I have further questions?   

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Missouri Route 19 Bridge Rehabilitation over Spring Creek in Dent County on your inquiries.  

How can I stay updated on the project’s progress?  

Sign up for project-specific updates using the form below.  

Project News

  • Public input sought on Dent County bridge project

    08/17/2026

    JEFFERSON CITY, Mo. – The Missouri Department of Transportation is seeking community input on a project to replace the driving surface of the Missouri Route 19 bridge over Spring Creek in Dent County, just south of Salem. Built in 1986the Spring Cr...

  • Planned Road Work for Mid-Missouri

    08/14/2026

    JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Aug. 17 - 23, 2026.  

    In addition to the work listed below, other moving operations such as pothole patching, mowing, ...

  • Dent County Route B now open at Dry Creek Bridge

    08/10/2026

    JEFFERSON CITY, Mo. – Dent County Route Bsouth of Salem, is now open. Construction crews completed the new bridge over Dry Creek and were able to reopen the road to all traffic today, Aug. 10. 

    Crews from Joe’s Bridge & Grading, Inc., working with...

Webform
Have Project Questions or Feedback? Use the form below to share your questions, thoughts and comments.
*
*

Your email address shared here will not be used for any purpose other than communicating about this project.

How did you hear about this project?
How clearly did the information on the website explain the project?
What is most important to you when considering this project?
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.