Project Milestones

Complete
Design
milestone_icon
Complete
Contractor Bids

The project was let in March 2018 allowing contractors to submit competitive bids for the project.

milestone_icon
Complete
Contract Awarded

The Missouri Highways and Transportation Commission reviewed all bids and awarded a contract to L.G. Barcus and Sons, Inc. at their April 2018 meeting.

milestone_icon
Complete
Contractor May Begin Work

The contract is allowed to begin work in May 2018. They planned to close the bridge to all  traffic the morning of May 2018.

milestone_icon
Complete
Completion

The contract completion date is September 7, 2018, though the contractor may finish the job before that date if factors allowed.

milestone_icon

Old Bridge

  • Built in 1934
  • Weight-limited bridge
  • 22 feet wide with two 10-foot lanes and one-foot shoulders

New Bridge

  • Meets current standards
  • Weight restrictions removed
  • 32 feet wide with two 12-foot lanes and four-foot shoulders

Frequently Asked Questions

 

Q: Why is MoDOT closing the road during construction?

  • closing the bridge saves taxpayer money by allowing the contractor to work more efficiently and will result in a shorter construction period.

Q: What is the current planned detour?

  • The proposed signed detour is over U.S. Route 36, Interstate 35 and Route 6.

Q: Why not build a bypass?

  • Based on the cost/benefit ratio, building a bypass would not be a good use of taxpayer funds.

Q: Do you have to buy any right of way?

  • Only the purchase of two construction easements is anticipated at this time.

Q: Who can I contact if I have further questions?

Q: How can I stay updated on the project's progress?

  • Sign up for project-specific updates below:

 

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).