Counties Impacted
Cape Girardeau
Route Impacted
Z
Work Type
Bridge Replacement
Planning Phase

Project Summary

The project will include replacing the Route Z bridges over Hubble Creek and Hubble Creek Overflow near Gordonville, Missouri. Both aging, one lane structures will be replaced with wider structures to accommodate two lanes of traffic. In addition, the project also includes raising the roadway to mitigate flooding on Route Z. 

As work is underway, the roadway will be closed in the vicinity of the structures for approximately eight months. 

There may be periods when the Route OO bridge over Whitewater River and the Route Z bridges over Hubble Creek and Hubble Creek Overflow are closed at the same time. Signed detours will be in place to maintain access during construction.

Prior to the start of construction for the Route OO and Route Z bridges, additional information will be released regarding the timeline for each closure. 

Project Timeline

Complete
Public Meeting
July 13, 2023
milestone_icon
Tentative Letting
Spring 2026
milestone_icon
Construction
As early as Summer 2026
milestone_icon
Anticipated Completion
Approximately 8 months following the start of construction
milestone_icon

Contact Us

Contact Photo
Seiji Shimbo_SE_Project Manager
Seiji Shimbo
Title
Project Manager
Department
Southeast District
Contact Info

(573) 472-5389