Bagnell Dam Bridge Rehabilitation
The Business 54 Bagnell Dam bridge over the Osage River, in Lake Ozark, was rehabilitated. The bridge was built in 1929 as part of the construction of the Bagnell Dam. The bridge reached a point where rehabilitation is necessary.
Project Details
When:
Construction began in September, 2021.
Cost:
The contracted cost for this project is $1,611,862.
Work Taking Place:
The purpose of this project was to repair the bridge deck, expansion joints and barrier walls and to replace the bridge driving surface and repair the adjacent sidewalk.
Project Milestones
The Missouri Highways and Transportation Commission awarded the project to Concrete Strategies, LLC., which submitted the low bid of $1,611,862.
Completed in June, 2022
News & Updates
-
Work Will Temporarily Close Bagnell Dam June 6-10
MILLER COUNTY – Weather permitting, contractors working for the Missouri Department of Transportation (MoDOT) plan to initiate the final phase of rehabilitating the bridge over Bagnell Dam at the Lake of the Ozarks next week.
Crews are currently... -
Bagnell Dam Bridge to Reopen Ahead of Upcoming Weekend
LAKE OZARK – The bridge across Bagnell Dam at the Lake of the Ozarks will reopen to traffic this Friday following a months-long rehabilitation project.
The bridge, which was closed in September, has received repairs to the bridge deck, expansion...
-
Rehabilitation of Bagnell Dam Bridge in Lake Ozark to be Extended
JEFFERSON CITY - Rehabilitation of the Business Route 54 Bagnell Dam bridge, located in Lake Ozark, will take longer than expected.
“As contractors have worked on the bridge, crews have discovered that the bridge deck is in worse condition than...