Write Up:
MoDOT’s customers expect transportation improvements to be completed and roadways opened quickly with minimal impact to their lives. Delivering projects by the contract completion date is the target for all projects and is considered a commitment to Missourians and drivers. Completing projects on time helps maintain credibility with Missourians, minimizes drivers’ exposure to work zones and provides facilities in good condition that improve safety and reduce vehicle maintenance costs.
MoDOT works to meet the initial contract completion date by preparing accurate plans and quantities, setting aggressive but reasonable completion dates and setting liquidated damages to reinforce completion dates without undue bid risks. In the first two quarters of fiscal year 2024, 74% of all closed-out projects were completed by their planned completion dates.
Weather, additional work or a MoDOT directive sometimes necessitates an authorized extension of the completion date without any financial assessment to the contractor. In the first two quarters of fiscal year 2024, 97% of the closed-out projects were completed by the adjusted dates.
There are times when a contractor misses the contract completion date, and the contractor is assessed damages. Of the road and bridge contracts completed in the first two quarters of fiscal year 2024 that did not meet the original contract date, 10 were extended due to extra work, 21 were extended by MoDOT, four were extended due to weather and five missed the completion date with damages assessed totaling $132,800.
The target for this measure is to have at least 80% of projects completed by the original completion date. At the end of FY 2023, the average number of all contracts completed by the original completion date was 70%.
Purpose of the Measure
This measure tracks the percentage of road and bridge projects opened by the commitment date established in the contract. This commitment also includes local public agency projects and multimodal projects (rail, aviation, waterway and transit).
Measurement and Data Collection:
For road and bridge projects, the project manager collaborates with the project team to establish the project completion day which is specific to when the road or bridge project will be opened to the public so to eliminate a financial penalty. The resident engineer uses the AASHTOWare system to track and document the work. Local public agencies and multimodal agencies use staff or consultant resources to set contract completion dates and track performance.
The target for this measure was set by management directive.
Results Driver
Brandi Baldwin
Title
State Construction and Materials Engineer
Department
Construction and Materials
Contact Info
Email: Brandi.Baldwin@modot.mo.gov
Phone: (573) 751-7455
Email: Brandi.Baldwin@modot.mo.gov
Phone: (573) 751-7455
Measurement Driver
Zakary Stokes
Title
Senior Construction Inspector
Department
Construction and Materials
Contact Info
Email: Zakary.Stokes@modot.mo.gov
Phone: (573) 301-6129
Email: Zakary.Stokes@modot.mo.gov
Phone: (573) 301-6129