Traffic Shifts Planned for Westbound I-70 Near Foristell as Pavement Work Continues

HANNIBAL – As work continues on the Improve I-70: Warrenton to Wentzville project, crews will shift westbound Interstate 70 traffic in the St. Charles County area, starting November 12. These shifts will take place near Foristell between the Warren/St. Charles County line and the Foristell Weigh Station (mile marker 202.8 – 205.4).

Traffic will shift onto the newly constructed pavement and existing driving lane to allow crews to construct the permanent passing lane and left shoulder.

To complete the traffic switch, westbound I-70 will be reduced to one lane during nighttime hours from 8 p.m. to 6 a.m. to allow for the repositioning of temporary barrier wall.

After the traffic switch occurs, motorists can expect the following traffic conditions and impacts through Spring/Summer of 2027:

  • Traffic barriers will be in place along the left shoulders of westbound and eastbound I-70 for this area.
  • Two lanes of traffic will be maintained on I-70 during peak travel times and the speed limit will remain 55 mph throughout the work zone.
  • Westbound I-70 will be reduced to one lane during nighttime hours of 8 p.m. to 6 a.m. All westbound lanes will continue to be narrowed.
  • Eastbound I-70 may have intermittent left lane closures during nighttime hours of 8 p.m. to 6 a.m.

Motorists are encouraged to pay attention in work zones, drive the posted work zone speed limit, and allow extra time for travel. All work is weather-dependent, and schedules are subject to change. 

Project Facts:

This work is part of the second project in MoDOT’s Statewide Improve I-70 Program. Improve I-70 Warrenton to Wentzville is a $600 million Design-Build project that will improve the 20-mile stretch of I-70 between Warrenton and Wentzville. The project was awarded to the Improve 70 Alliance team in November 2024.  Construction is anticipated to be complete by the end of 2028.

Missouri’s FY2024 budget, approved through the state legislative process and signed into law by the governor, provides $2.8 billion in General Revenue to build a third lane of I-70 across the state. The program will plan, design, construct, reconstruct, rehabilitate, and add a third lane in each direction on nearly 200 miles of I-70, from Blue Springs to Wentzville.

For more information on the Improve I-70 Program and to sign up for program e-mails, visit  http://www.modot.org/improvei70.  

                                                                ###

Districts Involved
St. Louis
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Media Inquiries
Real Time Traffic

Monitor real time traffic with our online traffic map.