JACKSON COUNTY – The Missouri Department of Transportation has scheduled several lane and ramp closures on I-435 from the Three Trails Crossing to State Line next week as crews continue paving operations. Schedule as follows:
- Monday, April 15: On westbound I-435, crews will CLOSE the second inside lane from the barrier from the Blue River Bridge near 103rd street to Holmes Road from 10 a.m. to 6 p.m. to work on new pavement. Crews will also CLOSE eastbound Holmes Road entrance ramp from 7 p.m. to 5 a.m. to pour new pavement near the top of the ramp.
- Tuesday, April 16: On westbound I-435, crews will CLOSE the second inside lane from the barrier from the Blue River Bridge near 103rd street to Holmes Road from 10 a.m. to 7:30 p.m. to work for the new pavement. They will also CLOSE the TWO inside lanes on westbound I-435 from Grandview Road to State Line Road from 7:30 p.m. to 5 a.m. to pour new pavement. This closure WILL LIKELY impact I-470 traffic heading into Three Trails Crossing.
- Wednesday, April 17: Crews will CLOSE the eastbound Holmes Road entrance ramp from 7 p.m. to 5 a.m. to pour new pavement near the top of the ramp. They will also CLOSE the eastbound Wornall Road exit ramp from 7:30 p.m. to 5 a.m. to remove barrier wall and for pavement grading on the ramp.
- Thursday, April 18: Crews will again CLOSE the TWO inside lanes westbound I-435 from Grandview Road to State Line Road from 7:30 p.m. to 5 a.m. for paving. This closure WILL LIKELY impact I-470 traffic heading into Three Trails Crossing. They will also CLOSE TWO lanes on eastbound I-435 from Holmes Road to Grandview Road at the same time for paving.
- Friday, April 19: TWO lanes of westbound I-435 from Grandview Road to State Line Road will be CLOSED from 7:30 p.m. to 5 a.m. for paving operations. This closure WILL LIKELY impact I-470 traffic heading into Three Trails Crossing.
Review the planned work on MoDOT’s Traveler Information Map at traveler.modot.org. To review the traffic impacts, visit KC Scout’s website at www.kcscout.net.
This work is part of the I-435 South Loop Link project which will replace the bridges at Wornall and Holmes, rehabilitate the bridges at 104th Street and the Blue River, upgrade the pavement on I-435 which includes adding another lane. Learn more about the project here: www.modot.org/kansascity/major_projects/I435South/.
Please remember that all work zones are NO PHONE zones. Buckle up. Phone down. Arrive Alive. Motorists are reminded to slow down and pay attention while driving in work zones. Not all work zones look alike. Work zones can be moving operations, such as striping, patching or mowing. They can also be short term, temporary lane closures to make quick repairs or remove debris from the roadway.
For more information about MoDOT news, projects or events, please visit our website at www.modot.mo.gov/kansascity. For instant updates, follow MoDOT_KC on Twitter, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for workzone updates or call 888-ASK-MODOT (275-6636).