The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of April 29- May 10, 2019. Weather conditions may postpone the work schedule. Many projects will include lane closures that could cause traffic delays.
MoDOT reminds motorists to buckle up, slow down, follow posted signs and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or visit www.modot.org/modot-central-district. You can also follow MoDOT’s Central Missouri District on Twitter and Facebook at https://twitter.com/MoDOT_Central and MoDOT Central Missouri District.
All Counties
Daylight Hours
Mowing, striping, brush cutting and guardrail repair continues in various locations. Motorists should travel with care and be alert to slow-moving equipment along the road.
Boone County
Overnight/Daylight Hours
Route 124 over Grindstone Creek, west of Route 63 – New bridge construction continues. The work is not expected to impact traffic.
- Grading and excavation work continues.
- Crews will be clearing the west side of the project.
- Construction of the new roadbed will begin.
- The project is scheduled for completion in December.
Route 163 (Providence Road) between Interstate 70 and Route K – Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in November.
Overnight Hours
Route 63 between Route 763 and the Randolph County line – Pavement repair work continues and crews will begin guardrail upgrades.
- Work continues at the Route 22 interchange. The work will result in periodic northbound and southbound ramp closures at the interchange.
- Guardrail upgrades will take place between Route 763 and Route 22. One lane will be open in each direction.
- The work is scheduled for completion in November.
Route 763 (College Avenue) between Route 740 (Stadium Boulevard) and Rollins Street – Pavement repair continues. One lane will be open through the work area. The project is scheduled for completion in November.
Daylight Hours
Route 163 between Route H and Route K – Roadway resurfacing and shoulder widening continues.
- Shoulder widening is expected to begin Monday, April 29. Beginning at Tom Bass Road and working westbound.
- The entire project is scheduled for completion in November.
Route K between Scott Boulevard and Burr Oak Road – Brush cutting will take place on Monday, April 29 and Friday, May 3. One lane will be open and crews will flag traffic through the work area.
Route O between Route UU and Grocery Branch Road – Brush cutting will take place on Monday, April 29 and Friday, May 3. One lane will be open and crews will flag traffic through the work area.
Route UU between Route O and Van Horn Tavern – Brush cutting will take place on Monday, April 29 and Friday, May 3. One lane will be open and crews will flag traffic through the work area.
Callaway County
Daylight Hours /Overnight Hours
Business Route 54 between the Route H and Route 54 interchange – Overnight pavement improvement operations continue. Work will take place between the hours of 7 p.m. and 7 a.m. One lane will be open and crews will flag traffic through the work area.
- In addition to the paving operations, various side street approaches are scheduled to be resurfaced within the work area.
- Resurfacing operation at Silver Drive continues. One lane of traffic will be open and crews will flag traffic through the work area.
- New asphalt shoulders will be constructed after the completion of Silver Drive operation.
Daylight Hours
Route O between State Street and Route D – Grading operations for shoulder addition will begin Monday, April 29. One lane will be open and crews will flag traffic through the work area.
Camden County
Daylight/Overnight Hours
Route 242 between Route 54 and Miller County line – Roadway resurfacing and shoulder widening begins Monday, April 29.
Route MM between Route 242 and Route TT – Roadway resurfacing and shoulder widening begins Monday, April 29.
Route KK between Osage Beach Parkway and Turkey Bend Road – Roadway resurfacing and shoulder widening begins Monday, April 29.
Overnight Hours
Route 5 between Route 7 and Route 64 in Laclede County – Pavement repair continues. One lane will be open and crews will flag traffic through the work area. The project is scheduled for completion in May.
Daylight Hours
Route 54 between Route KK and East Valley Drive – Pavement improvement and J-Turn installation continues. The project is scheduled for completion in August.
Route 54 at the Grand Glaze Bridge – Bridge maintenance will take place Thursday, May 2. One westbound lane will be open and crews will flag traffic through the work area.
Route 54 in Osage Beach – Pavement striping will take place Monday, April 21 through Tuesday, April 30 in various locations. One eastbound and one westbound lane will be open through the work area.
Route U between Route 54 and Whistle Road – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route Z between Route 7 and Dority Drive – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route DD between Route 7 and Coulter Street – Pavement repair will take place Monday, April 29 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Cooper County
Daylight Hours
Route 135 between Bock Street and Main Street – Sidewalk repairs continue. Much of the work will take place off the roadway. Minimal traffic interruptions are expected through the work area. The project is set for completion in July.
Route 87 between Route B and Route O in Moniteau County – Guardrail installation continues. One lane will be open and crews will flag traffic through the work area. The project is scheduled for completion in September.
Crawford County
Daylight Hours
Route 19 between Interstate 44 and Main Street – ADA sidewalk improvements will continue the week of April 29. One lane will be open and crews will flag traffic through the work area. The project is scheduled for completion in December.
Route 19 between Route O and Route P – Pavement striping will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route 19 between Route 49 and Route O – Pavement repair will take place Monday, April 22 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Route 49 between Route 19 and Route Y in Iron County – Pavement repair and edge rut repair will take place Monday, April 22 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Route C between Route 19 and Old Route 66 – Edge rut repair will take place on Monday, April 29 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Route N between Outer Road 44 and Washington County – Edge rut repair will take place on Monday, April 29 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Dent County
Daylight Hours
Route 32 between Route 72 and Route F – Shoulder work will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route WW between Route 19 and County Road 6255 – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Howard County
Daylight Hours
Route H over Salt Fork Creek, south of County Road 204 – Bridge maintenance will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area
Route V between Route 3 and Route 5 in Chariton County - Pavement repair will take place Monday, April 29 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area.
Route JJ between Route 3 and County Road 209 – Pavement repair will take place Thursday, May 2 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Laclede County
Daylight/Overnight Hours
Interstate 44 between mile marker 135 and mile marker – 145 – Bridge repair will take place on Tuesday, May 7. One lane will be open and crews will flag traffic through the work area.
Interstate 44 Outer Road over the Gasconade River, west of Route 133 – Bridge replacement continues. The road is currently closed. The entire project is scheduled for completion in August.
Route N between Route 32 and south Outer 44 – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Maries County
Daylight Hours
Route 63 between Route 68 and Interstate 44 in Phelps County – Grading, resurfacing, guardrail and rumble strip installation continues.
- Shoulder work and northbound acceleration lane construction continues at the intersection of Route 68. One lane will be open and crews will flag traffic through the work area.
- The project is scheduled for completion in November.
Miller County
Daylight/Overnight Hours
Route 54 over Business Route 54 in Eldon – Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in mid-May.
Route 54 over Old Tuscumbia Road, east of Route 52 – Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in mid-May.
Route 242 between Route 54 and Camden County line – Roadway resurfacing and shoulder widening begins Monday, April 29. Most of the work is expected to occur overnight in highly traveled areas. One lane will be open and crews will flag traffic through the work area.
Route A between Route 17 and 42 – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route BB between Route 42 and Maries County line - Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Moniteau County
Daylight/Overnight Hours
Route E over North Moreau Creek, south of Route 50 – Bridge deck replacement continues. The road is closed during the work. Motorists are advised to seek an alternate route around the work area. The project is scheduled for completion in mid-June.
Daylight Hours
Route 87 between Route O and Hazel Dell School Road in Cooper County – Pavement repair will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route 87 between Route O and Route 5 in Cooper County – Guardrail installation continues. One lane will be open and crews will flag traffic through the work area. The project is scheduled for completion in September.
Route C between Route 54 in Cole County and Route 52 in Morgan County – Guardrail installation continues. One lane will be open and crews will flag traffic through the work area.
Route KK between Route D and Gooseberry Hollow Road – Culvert pipe replacement will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Morgan County
Daylight Hours
Route 5 between Clay Road and Zulaue Street – Roadside maintenance will take place Monday, April 29 through Thursday, May 2. One lane will be open and crews will flag traffic through the work area
Route 52 between Route FF and Cedar Lane – Culvert pipe replacement will take place on Monday, April 29. One lane will be open and crews will flag traffic through the work area.
Route C between Route 52 and Route 54 in Cole County – Guardrail installation continues. One lane will be open and crews will flag traffic through the work area.
Phelps County
Daylight/Overnight Hours
Route 63 between Interstate 44 and Route CC – Roadway and sidewalk repair continues.
- Sidewalk repair during the daytime hours continues. One lane will be open through the work area.
- Concrete pavement repair during the nighttime hours between Olive Street and Vichy Road will begin on Monday, April 15. One lane will be closed at a time and the middle turn lane will be used for through traffic. There will also be brief periods of one lane traffic, with workers flagging traffic through the work area.
- The project is scheduled for completion in October.
Daylight Hours
Route 63 between Interstate 44 and Route 68 in Maries County – Grading, resurfacing, guardrail and rumble strip installation will continue.
- Shoulder work and northbound acceleration lane construction continues at the intersection of Route 68. One lane will be open and crews will flag traffic through the work area.
- The project is scheduled for completion in November.
Route 8 between Route 63 and Crawford County Line – Brush cutting will take place Monday, April 29 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route J between Interstate 44 and Route K – Edge rut repair will take place Monday, May 6 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Outer Road 44 (Arlington Road) between Interstate 44 and County Road 7300 – Edge rut repair will take place Monday, April 29 through Friday, May 10. One lane will be open and crews will flag traffic through the work area.
Pulaski County
Daylight Hours
Route 7 over the Gasconade River, south of Rio Road – Bridge painting will begin on Monday, April 29. Minimal traffic impacts are expected. Project is scheduled for completion in June.
Route 133 over Interstate 44 - Bridge maintenance will take place Thursday, May 1. One lane will be open and crews will flag traffic through the work area.
Washington County
Daylight/Overnight Hours
Route 185 over Fourche Renault Creek, south of Fourche Renault Road – Bridge rehabilitation continues. The road will be closed during the work. Motorists are advised to seek an alternate route around the work area. The project is scheduled for completion in mid-June.
Daylight Hours
Route 21 between Route 8 and Route 32 – Pavement repair will take place Monday, April 29 through Thursday, May 2. One lane will be open through the work area.
Route 21 between the Jefferson County line and Route 32 in Iron County – Roadway resurfacing and sidewalk repair continues.
- Roadway paving will continue the week of, April 29. One lane will be open and crews will flag traffic through the work area.
- Guardrail work south of Caledonia continues. One lane will be open and crews will flag traffic through the work area.
- The project is scheduled for completion in November.
Route 185 east of Rabbit Hollow Road – Culvert pipe repair will take place Monday, May 6 through Thursday, May 9. One lane will be open and crews will flag traffic through the work area.
Route A over Indian Creek, north of Willow Road – Bridge maintenance will take place Monday, April 29 and Tuesday, April 30. One lane will be open and crews will flag traffic through the work area.
MoDOT encourages motorists to log on to wwww.modot.org/modot-central-district to comment on their experiences traveling through highway work zones.
###