Intersection Safety and Resurfacing Projects Coming To Route 160/13

From Springfield to Kimberling City Starting Week of July 1

Greene, Christian and Stone Counties – Drivers can expect nighttime lane closings beginning the week of July 1 when crews begin making intersection safety improvements along Route 160/13 between Plainview Road in Springfield and Business 13 in Stoneridge north of Kimberling City, the Missouri Department of Transportation said. 

The project targets 19 intersections along the Route 160/13 corridor with contractor crews beginning work in the Nixa area. 

Much of the work will take place at night with lane closings limited to the hours of 8 p.m. to 6 a.m. 

For the first couple of weeks in July, drivers will see work zone signs and other work zone items installed. The actual work to build the improvements will start in mid-July. 

Traffic Impacts: 

Drivers can expect flaggers on the road, directing them through the work zones. Drivers are also urged to follow pilot cars. Drivers on side roads should wait for the pilot vehicles before pulling onto Route 160/13. 

Side roads could have lane reductions or could be closed at times. During full closings, drivers are urged to seek alternate routes. 

People who live along Route 160/13 where the work is taking place could experience noisy conditions at night during the work. 

Here’s a look the intersection/resurfacing projects: 

  • At Plainview Road in Springfield – extend southbound through-lane to Farm Road 157 
  • At Greene County Farm Road 157 – build J-turn that uses turn-around points at Plainview Road and Farm Road 186
    • Left-turns from Farm Road 157 will be prohibited. 
  • At Greene County Farm Road 192 – add northbound right turn lane
    • Left-turns from Farm Road 192 will be prohibited. 
  • At Bentwater Drive in Nixa – southbound offset right turn lane 
  • At Tracker Road in Nixa
    • Offset left-turn lanes on Route 160/13
    • Eastbound dual left-turn lanes
    • Eastbound right-turn lane 
  • At Aldersgate Drive in Nixa – northbound and southbound offset left-turn lanes 
  • At Northview Road in Nixa
    • Widening Northview Road from Foxwood Drive to Route 160/13 (Project funded by the City of Nixa.)
    • Improve turning movements and traffic signal improvements
    • Add crosswalks and pedestrian crossing to traffic signal 
  • At Wasson Drive in Nixa – northbound and southbound offset left-turn lanes 
  • At Citydel Road in Nixa – lengthen turn lane 
  • At Rosedale Road south of Nixa – Improve visibility at intersection
    • Construct southbound right-turn lane
    • Drainage and slope improvements in remaining three corners to relocate guardrail for better visibility
    • Lengthen turn lane 
  • At Pawnee Road south of Nixa
    • Install new guardrail north of Pawnee Road on east side
    • Lengthen turn lane 
  • At Primrose Road south of Nixa – lengthen turn lane 
  • At Riverdale Drive south of Nixa – lengthen southbound turn lane 
  • At Melton Avenue north of Highlandville – lengthen turn lane 
  • At Kentling Avenue in Highlandville – lengthen turn lane 
  • At Coon Ridge Road north of Reeds Spring – lengthen turn lane 
  • At Route 248/160/13 at Reeds Spring Junction – construct northbound right turn lane 
  • At Business 13 North and Route 413 in Branson West
    • Construct northbound acceleration lane
    • Build offset left-turn lanes on Business 13/Route 413 
  • Business 13 North in Stoneridge – pavement repair 
  • Resurface Route 160/13 between Plainview Road in Springfield and the Kimberling City bridge. The resurfacing is scheduled to begin in mid-August and will be done at night. The work includes grinding off the old asphalt in areas and laying a new asphalt driving surface. 

Weather and/or construction delays could alter the work schedule. 

The intersection projects at Tracker Road and at Northview Road in Nixa are a partnership between MoDOT and the City of Nixa. 

The intersection projects are scheduled for completion in mid-April 2020. 

The resurfacing project is scheduled for completion by early November 2019.

 The prime contractor on all projects is APAC-Central of Springfield.

 The total project cost is $15.1 million.  

  END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com)

Districts Involved
Southwest