Route 65: THE REBUILD The Final Phase - Springfield

Update for Week of July 28
  • Nighttime lane closings on Route 65 for prep work
  • Detour signing and electronic message boards deployed throughout Springfield metro area
  • Southbound Route 65 CLOSED between Sunshine St. and Battlefield Rd. August 4-10

Work Scheduled:  

  • Installing erosion control devices in areas
  • Cutting concrete pavement in southbound lanes of Route 65 between Sunshine Street and Battlefield Road
  • Installing detour signs along I-44, Route 125, Route 60 and Route 360
  • Deploying electronic message signs in various locations throughout Springfield metro area 

Traffic Impacts:  

  • Nighttime lane closings on Route 65 between Sunshine Street and Battlefield Road. At least one lane in each direction will remain open during the work.
    • Work hours: 8 p.m. until 6 a.m. Wednesday through Friday, July 31-August 2.
  • Crews and equipment entering and leaving work areas
  • Temporary traffic signals flashing at Blackman Road/Battlefield Road and Greene County Route D/Missouri Route 125 intersections (Signals go into full operation around noon on Saturday, August 3.) 

(Weather or construction delays could alter the work schedule.) 

Project Summary: 

  • Wednesday-Friday, July 31-August 2
    • Nighttime lane closings on southbound Route 65 
  • Sunday-Saturday, August 4-10
    • All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
    • Southbound on ramp from Sunshine Street to Route 65 CLOSED
    • Southbound off ramp from Route 65 to Battlefield Road CLOSED
    • Southbound Route 65 lanes will close at 12:01 a.m. on Sunday, August 4, and reopen 
  • Saturday-Tuesday, August 10-20
    • All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
    • Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
    • Southbound on ramp from Battlefield Road to Route 65 CLOSED
    • Southbound Route 65-to-westbound Route 60 ramp CLOSED 

All lanes of Route 65 open during the Labor Day holiday (Tuesday-Friday, August 20-September 6) 

  • Friday-Saturday, September 6-14
    • All northbound lanes of Route 65 CLOSED between Route 60 and Battlefield Road
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Northbound off ramp from Route 65 to Battlefield Road CLOSED 
  • Saturday-Friday, September 14-20
    • All northbound lanes of Route 65 CLOSED between Battlefield Road and Sunshine Street
    • Northbound Route 65 OPEN between Route 60 and Battlefield Road, but reduced to one lane
    • Northbound on ramp from Battlefield Road to Route 65 CLOSED
    • Northbound off ramp from Route 65 to Sunshine Street CLOSED
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J 
  • September 20-November 1
    • Nighttime lane closings for shoulder construction/guardrail/striping 
  • Prime Contractor: Emery Sapp and Sons, Inc. of Columbia
  • Completion Date: November 2019 (However, contractor plans to complete project by late September.)
  • Total Project Cost: $8.1 million

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.