The meeting will allow those interested to learn about plans for a 2027 project to make repairs along the corridor and share their thoughts about the project. Work includes:
- Pavement repairs where needed and roadway resurfacing along I-44 between Eureka and Valley Park.
- Repairing several bridges on I‑44.
- Replacing the I-44 bridges at Williams Creek and improving culverts in the area.
- Rebuilding the interstate median barrier.
- Adding safety improvements at Antire Hill.