Where: U.S. Route 60 & Newton County Route HH east of Neosho
When: Beginning week of November 24 for up 45 days
What: New traffic pattern while contractor crews continue intersection improvements
Traffic Impacts:
- South side of U.S. Route 60/Route HH intersection CLOSED for up to 45 days beginning week of November 24
- Route HH traffic approaching Route 60 from the south will have no access to Route 60 while intersection is CLOSED
- Drivers will have access to all businesses south of Route 60
- Route HH will be CLOSED between Route 60 and Mallard Drive
- Drivers traveling east- or westbound on Route 60 will not be affected, but will have no access to Route HH south of the intersection
- Route HH (Carl Sweeney Parkway) traffic approaching from the north will have access to Route 60 via the newly completed roundabout
- No signed detours
- Drivers urged to find alternate routes
- Signs and message boards will alert drivers approaching the work zone
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or scheduling conflicts could alter the work schedule.
This work is part of a project to make improvements at six (6) intersections along U.S. Route 60 between Newton County Route Y east of Seneca and Missouri Route 97 in Barry County near the Monett Regional Airport. More information can be found by going to the project website.
Project Information:
- Contractor: Capital Paving & Construction Co., Springfield
- Completion Date: December 1, 2026
- Total Cost: $9.7 million
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest