ST. JOSEPH, Mo. – The Missouri Department of Transportation has contracted Above & Below Contracting, LLC for a resurfacing project that will lengthen the lifespan of roadways in three counties. The project is scheduled to begin Thursday, Sept. 4. The contractor’s tentative schedule is as follows:
- Sept. 4 – Nodaway County Route JJ.
- Sept. 6 – Nodaway County Route NN.
- Sept. 13 – Nodaway County Route AB.
- Sept. 16 – Nodaway County Route WW .
- Sept. 22 – Nodaway County Route AH.
- Sept. 29 – Nodaway/Andrew counties Route N.
- Oct. 3 – Nodaway/Andrew counties Route Y.
- Oct. 10 – Holt County Route C.
Traffic Impacts: During resurfacing, each route may be closed in up to 2-mile sections. Motorists will need to seek an alternate route during the closures.
All routes are anticipated to be complete by mid-October 2025.
All work is weather permitting and could be rescheduled. Project schedule updates will be provided on the Traveler Information Map (http://traveler.modot.org/map/) and on the Planned Roadwork for Northwest Missouri press release sent out each Friday afternoon. The press release can be viewed by signing up for eUpdates at MoDOT E-Updates.
MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones. Know before you go and check what work zones you might encounter at traveler.modot.org.
Get project and work zone news straight to your email by signing up for eUpdates. Information is also available 24/7 by calling 888-ASK-MODOT (275-6636) or visiting www.modot.org/northwest.
Take the Challenge! Buckle Up/Phone Down
###
Traveler Information Map
http://traveler.modot.org/map/