Multi-county scrub seal project to begin July 28

Atchison, Nodaway, Holt, Gentry, Worth, Harrison, and Daviess counties

ST. JOSEPH, Mo. – The Missouri Department of Transportation has contracted Vance Brother Inc. for a scrub seal project that will lengthen the lifespan of roadways in seven counties. The project is scheduled to begin Monday, July 28. The contractor’s tentative schedule is as follows:

  • July 28 – Atchison County Route CC
  • July 30 – Atchison County Route KK
  • Aug. 1 – Atchison County Route Z
  • Aug. 5 – Nodaway County Route D
  • Aug. 6 – Nodaway/Atchison County Route C
  • Aug. 11 – Nodaway County Route KK
  • Aug. 13 – Nodaway County Route PP
  • Aug. 15 – Atchison County Route EE
  • Aug. 18 – Holt/Nodaway County Route DD
  • Aug. 20 – Holt County Route HH
  • Aug. 21 – Holt County Route B
  • Aug. 26 – Holt County Route H
  • Aug. 27 – Holt County Route BB
  • Aug. 28 – Holt County Route T
  • Sept. 2 – Nodaway/Gentry County Route M
  • Sept. 8 Gentry/Worth counties Route N
  • Sept. 11 – Harrison County Route EE
  • Sept. 15 – Harrison/Gentry counties Route ZZ
  • Sept. 18 – Daviess County Route AA

Traffic Impacts: During the scrub seals, each route will be reduced to one lane with a pilot car guiding motorists through the work zone. A 10-foot width restriction will be in place.

Crews are scheduled to work 7 a.m.-8 p.m. Monday-Friday. All routes are anticipated to be complete by October 2025.

Project schedule updates will be provided on the Traveler Information Map (http://traveler.modot.org/map/) and on the Planned Roadwork for Northwest Missouri press release sent out each Friday afternoon. The press release can be viewed by signing up for eUpdates at  MoDOT E-Updates.

All work is weather permitting and could be rescheduled.

MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones. Know before you go and check what work zones you might encounter at traveler.modot.org.

Get project and work zone news straight to your email by signing up for eUpdates. Information is also available 24/7 by calling 888-ASK-MODOT (275-6636) or visiting www.modot.org/northwest.

Facebook | X | Instagram  

Take the Challenge! Buckle Up/Phone Down

###

Traveler Information Map

http://traveler.modot.org/map/

Districts Involved
Northwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Media Inquiries
Katelyn Canon
Katelyn Canon
Sr. Communications Specialist
Northwest District

Email: nwcr@modot.mo.gov

Phone:  816.387.2462

Real Time Traffic

Monitor real time traffic with our online traffic map.