Beginning the Week of July 28 for Resurfacing Work
Where: Nighttime lane Closures on Chestnut Expressway between Eastgate Avenue and Farm Road 115/Broadview Place in Springfield
When: 8 p.m. – 6 a.m. beginning July 28 until completed
What: Contractor crews to resurface Chestnut Expressway (Business 65) as part of the Chestnut Expressway Safety and Operational Improvements in Greene
Traffic Impacts:
- Nighttime lane Closures on Chestnut Expressway between Eastgate Avenue and Farm Road 115/Broadview Place in Springfield
- Crews and equipment close to traffic in areas
- Electronic message boards located near the planned road work will alert drivers to any changes in the work schedule
- Check MoDOT’s Traveler Information Map for road closures/traffic impacts
Weather and/or construction delays will alter the work schedule.
Project Information:
- Blevins Asphalt Construction Co, Inc., Mt. Vernon is doing the work for a low bid amount of $9.4 million
- The project is to be completed by June 30, 2026
- Project website: Chestnut Expressway Safety and Operational Improvements in Greene
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube
Take the Challenge! Buckle Up/Phone Down
Districts Involved
Southwest
Published On