Where: Nighttime lane Closures along I-44 in Newton, Jasper, Lawrence, and Greene counties between Main Street (Missouri Route 43) in Joplin to Missouri Route 125 in Strafford
When: 8 p.m. – 6 a.m. beginning Monday, July 21, until late September
What: Contractor crews will be collecting core samples for the Forward 44 project. Crews will begin on I-44 near Main Street in Joplin and work their way east toward Missouri Route 125 in Strafford.
Traffic Impacts:
- I-44 nighttime lane Closures in Newton, Jasper, Lawrence, and Greene Counties between Main Street (Missouri Route 43) in Joplin to Missouri Route 125 in Strafford
- Crew and equipment close to traffic
- No signed detour. Drivers should find alternate routes.
- Signs and message boards will alert drivers approaching the work zones
- Check MoDOT’s Traveler Information Map for road closures/traffic impacts
Weather and/or construction delays could alter the work schedule.
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube
Take the Challenge! Buckle Up/Phone Down